Start with the route, not the room
The largest single item on a chiller is not the compressor but the route it took to get there. A 500 kW screw chiller is typically 3.5–4.5 m long, 1.6–2.0 m wide and weighs 4–7 tonnes. Before layout, confirm:
| Item | Check |
|---|---|
| Door and hatch sizes | Width, height and diagonal clearance |
| Corridor turns | Turning circle with the skid, not the bare unit |
| Floor loading on the route | Point loads during transport |
| Lifting points | Crane or gantry capacity at the final position |
| Roof access | Opening size, and whether the unit arrives in sections |
If the unit cannot pass, the options are to remove a wall, crane it in before the roof is closed, or specify a modular chiller. All three are cheaper than discovering the problem on delivery day.
Tube pull space is the dimension most often lost
Condenser and evaporator tubes are removed for cleaning or replacement, and they come out along the axis of the shell. Leave clear space equal to the shell length plus 0.5 m at one end, and do not put a pipe run, cable tray or wall in that zone.
| Vessel | Space required at the end | Consequence if lost |
|---|---|---|
| Evaporator | Shell length + 0.5 m | Tubes cannot be brushed; chemical cleaning only |
| Condenser | Shell length + 0.5 m | Same, plus no tube replacement |
| Both | 1.0–1.5 m working width | Maintenance access |
Where the space genuinely does not exist, specify removable end covers and a hinged door, and record the limitation in the O&M manual. Do not assume a future contractor will find a way.
Clearances and working space
| Location | Minimum | Note |
|---|---|---|
| Between chiller and wall | 1.0 m | 1.2 m if the control panel is on that side |
| Between two chillers | 1.2 m | Enough to open panels and isolate |
| Above the unit | 0.8 m | Compressor lifting and valve access |
| In front of the control panel | 1.2 m | Electrical safety working distance |
| Around the oil cooler | 0.8 m | Service access |
| Air-cooled condenser face to wall | 2.0 m | Recirculation risk below this |
| Between air-cooled units | 1.5 m | Two rows need a wider gap |
Air-cooled chillers also need the discharge plume to escape. A unit at the bottom of a light well will recirculate and lose 10%–20% of capacity in summer; the well has to be open on at least two sides, or the units have to be ducted.
Floor loading and vibration
| Chiller type | Typical operating weight | Point load (4 points) |
|---|---|---|
| 100 kW air-cooled | 1.2–1.6 t | 4–5 kN |
| 300 kW air-cooled | 2.8–3.6 t | 9–12 kN |
| 300 kW water-cooled screw | 3.5–4.5 t | 12–15 kN |
| 800 kW centrifugal | 8–12 t | 25–35 kN |
Add 50% for dynamic allowance at the compressor end. Chillers are usually mounted on spring isolators or neoprene pads; springs are preferred where the plant room is above occupied space, because they isolate the low-frequency component that pads do not.
| Isolation | Effective above | Deflection | Use |
|---|---|---|---|
| Neoprene pad | Above 20 Hz | 3–6 mm | Ground floor, slab on grade |
| Rubber-cork | Above 15 Hz | 5–8 mm | General |
| Spring | Above 5 Hz | 25–50 mm | Upper floors, sensitive spaces |
| Spring plus inertia base | Above 4 Hz | 25–50 mm | Hospital, auditorium |
Flexible connectors on the water pipes and a flexible electrical conduit are part of the same isolation package. A chiller on springs with rigid pipework transmits vibration straight through the pipes.
Heat rejection and ventilation
Water-cooled chillers reject heat to the cooling tower, but the plant room still gains heat from the compressor, the oil cooler and the pipework — roughly 2%–4% of cooling capacity. A 500 kW chiller adds 10–20 kW of heat to the room.
| Plant | Ventilation requirement |
|---|---|
| Water-cooled, small | 6 air changes per hour, or mechanical supply |
| Water-cooled, large | Calculate on 3% of capacity plus motor losses |
| Air-cooled (indoor) | Ducted inlet and discharge, sized on coil face velocity |
| Any plant with refrigerant | Emergency extraction at low level, alarm |
Refrigerant detection and low-level extraction are required in most codes for plant rooms above a threshold charge. Confirm the local requirement before the room is built, because retrofitting extraction into a finished room is expensive.
Drainage and housekeeping
| Item | Requirement |
|---|---|
| Floor drain | At the lowest point, trapped, sized for the largest vessel drain |
| Drain-down point | Every low point, with a valve and cap |
| Bund or curb | Around the chiller if a refrigerant or oil leak is possible |
| Water treatment | Sample point and dosing tank near the make-up |
| Cleaning access | Hose point within 10 m of the tube ends |
A chiller that is drained for maintenance releases several hundred liters. If the floor falls the wrong way, that water finds the electrical panel.
Electrical supply and control interfaces
| Item | Typical requirement |
|---|---|
| Supply | 380–415 V, 3-phase, 50 Hz |
| Voltage tolerance | ±10% |
| Cable entry | Bottom or side, with a gland plate |
| Isolation | Lockable isolator within sight |
| Earth | ≤ 4 Ω, separate earth bar |
| Control | Volt-free contacts for run, alarm, remote on/off |
| BMS | Modbus RTU/TCP or BACnet, with a point list |
Ask for the point list at design stage, not at commissioning. A chiller that cannot report its alarm to the BMS will be discovered by the tenant, not the engineer.
Longkang Environmental Equipment Co., Ltd. issues a dimension drawing with the rigging weight, center of gravity, tube pull space and connection positions marked, so the plant room can be set out before the unit is ordered. Phone: +86 400-878-0280 | +86 130-0200-1280
Questions from plant room designers
How much space does a 500 kW chiller need?
Plan on about 5 m × 3 m for the unit plus working space, giving a footprint of roughly 15–20 m² including clearances. Add the tube pull zone at one end, which alone may need 5 m.
Can a chiller be installed outdoors?
Air-cooled units are designed for it. Water-cooled units are not: the shell, the panel and the insulation all suffer. If a water-cooled machine must go outside, it needs a weatherproof enclosure with ventilation, and the warranty terms should be confirmed in writing.
Does the plant room need heating?
It needs frost protection. Keep the room above 5 °C, or drain the circuits and the vessels if the plant will be idle in freezing weather. A chiller left full of water in an unheated room will crack a tube.
How wide must the door be?
At least the unit width plus 200 mm, and ideally 300 mm, with the height checked against the skid. Where the door is narrower than the unit, the unit must be dismantled or the wall opened. Confirm before ordering.
Is a concrete inertia base necessary?
Only for upper-floor plant or where the structure is lightweight. On grade, spring isolators on a levelled plinth are usually enough. An inertia base adds 30%–50% to the isolated mass and improves low-frequency attenuation.
What clearance is needed for condenser cleaning?
Enough to remove the end cover and insert a brush or a rod: shell length plus 0.5 m, plus room to stand. Chemical cleaning needs less space but is slower and produces waste that must be handled.