Heat pumps · Chillers · Sludge drying systems
Knowledge

Water Chiller Installation: Plant Room Layout and Services

Start with the route, not the room

The largest single item on a chiller is not the compressor but the route it took to get there. A 500 kW screw chiller is typically 3.5–4.5 m long, 1.6–2.0 m wide and weighs 4–7 tonnes. Before layout, confirm:

Item Check
Door and hatch sizes Width, height and diagonal clearance
Corridor turns Turning circle with the skid, not the bare unit
Floor loading on the route Point loads during transport
Lifting points Crane or gantry capacity at the final position
Roof access Opening size, and whether the unit arrives in sections

If the unit cannot pass, the options are to remove a wall, crane it in before the roof is closed, or specify a modular chiller. All three are cheaper than discovering the problem on delivery day.

Tube pull space is the dimension most often lost

Condenser and evaporator tubes are removed for cleaning or replacement, and they come out along the axis of the shell. Leave clear space equal to the shell length plus 0.5 m at one end, and do not put a pipe run, cable tray or wall in that zone.

Vessel Space required at the end Consequence if lost
Evaporator Shell length + 0.5 m Tubes cannot be brushed; chemical cleaning only
Condenser Shell length + 0.5 m Same, plus no tube replacement
Both 1.0–1.5 m working width Maintenance access

Where the space genuinely does not exist, specify removable end covers and a hinged door, and record the limitation in the O&M manual. Do not assume a future contractor will find a way.

Clearances and working space

Location Minimum Note
Between chiller and wall 1.0 m 1.2 m if the control panel is on that side
Between two chillers 1.2 m Enough to open panels and isolate
Above the unit 0.8 m Compressor lifting and valve access
In front of the control panel 1.2 m Electrical safety working distance
Around the oil cooler 0.8 m Service access
Air-cooled condenser face to wall 2.0 m Recirculation risk below this
Between air-cooled units 1.5 m Two rows need a wider gap

Air-cooled chillers also need the discharge plume to escape. A unit at the bottom of a light well will recirculate and lose 10%–20% of capacity in summer; the well has to be open on at least two sides, or the units have to be ducted.

Floor loading and vibration

Chiller type Typical operating weight Point load (4 points)
100 kW air-cooled 1.2–1.6 t 4–5 kN
300 kW air-cooled 2.8–3.6 t 9–12 kN
300 kW water-cooled screw 3.5–4.5 t 12–15 kN
800 kW centrifugal 8–12 t 25–35 kN

Add 50% for dynamic allowance at the compressor end. Chillers are usually mounted on spring isolators or neoprene pads; springs are preferred where the plant room is above occupied space, because they isolate the low-frequency component that pads do not.

Isolation Effective above Deflection Use
Neoprene pad Above 20 Hz 3–6 mm Ground floor, slab on grade
Rubber-cork Above 15 Hz 5–8 mm General
Spring Above 5 Hz 25–50 mm Upper floors, sensitive spaces
Spring plus inertia base Above 4 Hz 25–50 mm Hospital, auditorium

Flexible connectors on the water pipes and a flexible electrical conduit are part of the same isolation package. A chiller on springs with rigid pipework transmits vibration straight through the pipes.

Heat rejection and ventilation

Water-cooled chillers reject heat to the cooling tower, but the plant room still gains heat from the compressor, the oil cooler and the pipework — roughly 2%–4% of cooling capacity. A 500 kW chiller adds 10–20 kW of heat to the room.

Plant Ventilation requirement
Water-cooled, small 6 air changes per hour, or mechanical supply
Water-cooled, large Calculate on 3% of capacity plus motor losses
Air-cooled (indoor) Ducted inlet and discharge, sized on coil face velocity
Any plant with refrigerant Emergency extraction at low level, alarm

Refrigerant detection and low-level extraction are required in most codes for plant rooms above a threshold charge. Confirm the local requirement before the room is built, because retrofitting extraction into a finished room is expensive.

Drainage and housekeeping

Item Requirement
Floor drain At the lowest point, trapped, sized for the largest vessel drain
Drain-down point Every low point, with a valve and cap
Bund or curb Around the chiller if a refrigerant or oil leak is possible
Water treatment Sample point and dosing tank near the make-up
Cleaning access Hose point within 10 m of the tube ends

A chiller that is drained for maintenance releases several hundred liters. If the floor falls the wrong way, that water finds the electrical panel.

Electrical supply and control interfaces

Item Typical requirement
Supply 380–415 V, 3-phase, 50 Hz
Voltage tolerance ±10%
Cable entry Bottom or side, with a gland plate
Isolation Lockable isolator within sight
Earth ≤ 4 Ω, separate earth bar
Control Volt-free contacts for run, alarm, remote on/off
BMS Modbus RTU/TCP or BACnet, with a point list

Ask for the point list at design stage, not at commissioning. A chiller that cannot report its alarm to the BMS will be discovered by the tenant, not the engineer.

Longkang Environmental Equipment Co., Ltd. issues a dimension drawing with the rigging weight, center of gravity, tube pull space and connection positions marked, so the plant room can be set out before the unit is ordered. Phone: +86 400-878-0280 | +86 130-0200-1280

Questions from plant room designers

How much space does a 500 kW chiller need?

Plan on about 5 m × 3 m for the unit plus working space, giving a footprint of roughly 15–20 m² including clearances. Add the tube pull zone at one end, which alone may need 5 m.

Can a chiller be installed outdoors?

Air-cooled units are designed for it. Water-cooled units are not: the shell, the panel and the insulation all suffer. If a water-cooled machine must go outside, it needs a weatherproof enclosure with ventilation, and the warranty terms should be confirmed in writing.

Does the plant room need heating?

It needs frost protection. Keep the room above 5 °C, or drain the circuits and the vessels if the plant will be idle in freezing weather. A chiller left full of water in an unheated room will crack a tube.

How wide must the door be?

At least the unit width plus 200 mm, and ideally 300 mm, with the height checked against the skid. Where the door is narrower than the unit, the unit must be dismantled or the wall opened. Confirm before ordering.

Is a concrete inertia base necessary?

Only for upper-floor plant or where the structure is lightweight. On grade, spring isolators on a levelled plinth are usually enough. An inertia base adds 30%–50% to the isolated mass and improves low-frequency attenuation.

What clearance is needed for condenser cleaning?

Enough to remove the end cover and insert a brush or a rod: shell length plus 0.5 m, plus room to stand. Chemical cleaning needs less space but is slower and produces waste that must be handled.

Related reading

Frequently asked questions