220 V or 380 V: Choosing the Power Supply for a Heat Pump

What the two supplies actually are

Item Single phase Three phase
Nominal voltage 220–240 V line to neutral 380–400 V line to line, 220–230 V line to neutral
Conductors Line, neutral, earth Three lines, neutral, earth
Typical domestic supply 40–63 A per household 3 × 25 A to 3 × 63 A
Availability Everywhere Most commercial buildings; not all houses
Unit capacity range 1.5–12 kW (up to 15 kW on some models) 10–500 kW

The voltage figures are nominal. A single-phase supply that measures 205 V at the unit on a summer afternoon is already at the −10% tolerance limit and will raise the compressor current; the installer should measure at the unit terminals under load, not at the meter.

Current draw, capacity by capacity

For a heat pump, the electrical input is the heating capacity divided by COP. A 12 kW unit at COP 3.6 draws 3.3 kW; a 40 kW unit at COP 3.4 draws 11.8 kW.

Heating capacity Approx. input at COP 3.4 Single phase 230 V Three phase 400 V
5 kW 1.5 kW 6.9 A 2.3 A per phase
10 kW 2.9 kW 13.4 A 4.5 A per phase
15 kW 4.4 kW 20.4 A 6.8 A per phase
20 kW 5.9 kW 27.3 A 9.1 A per phase
30 kW 8.8 kW 40.8 A 13.6 A per phase
40 kW 11.8 kW 54.3 A 18.1 A per phase

Single-phase current is input power ÷ (voltage × power factor), with a power factor of about 0.95 for an inverter-driven unit. Three-phase current is input ÷ (√3 × 400 × 0.95).

The practical limit for single phase is not the unit but the supply. A 40 A household supply cannot carry a 30 kW heat pump plus a cooker, a water heater and lighting. Above about 12 kW the single-phase option stops making sense even where a unit exists, because the cable and breaker become unreasonable.

Cable and protection

Item Single phase, 10 kW Three phase, 30 kW
Running current 13.4 A 13.6 A per phase
Breaker (motor-rated, type C or D) 20 A 20 A per phase
Cable, 15 m run 4 mm² 4 mm²
Cable, 40 m run 10 mm² 6 mm²
Voltage drop at full load, 40 m about 3.5% about 1.2%
Earth leakage protection 30 mA type A 30 mA type A, or type B if required

Two details catch people out. First, inverter-driven units produce high-frequency leakage current and can trip a 30 mA RCD that also protects other circuits; use a dedicated RCD, or a type B device where the manufacturer requires it, and never omit the RCD because it tripped once. Second, motor-rated breakers are needed because the starting current of a fixed-speed compressor is 5–7 times running current — a type B breaker will trip on a hot day even though the circuit is correct.

Starting current and why inverters change the answer

A fixed-speed compressor starting direct-on-line draws 5–7 times its running current for 0.3–1 second. On a 10 kW single-phase unit that is 80–95 A — enough to flicker lights on the same supply and, on a weak rural network, enough to trip the meter’s main switch.

An inverter unit ramps instead, typically limiting starting current to 1.2–1.5 times running current. That is the main technical reason inverter models dominate domestic and small commercial installations: not the part-load efficiency, but the fact that they can start on a supply that could not otherwise carry them.

Compressor type Starting current multiple Effect on supply
Fixed speed, direct on line 5–7 × May require soft starter
Fixed speed with soft starter 2.5–3 × Acceptable on most supplies
Inverter, ramped 1.2–1.5 × Starts on marginal supplies

Phase balancing when several single-phase units are used

A common commercial compromise is three single-phase units of 8–10 kW, one per phase, which gives 24–30 kW of heating without a three-phase supply upgrade. It works, but only if the phases are actually balanced and the units are controlled together.

Phase Unit Running current Balanced?
L1 Unit 1, 10 kW 13.4 A Yes
L2 Unit 2, 10 kW 13.4 A Yes
L3 Unit 3, 10 kW 13.4 A Yes
N Unbalanced return under 2 A Acceptable

Rules for this arrangement: keep the three units on the same nominal capacity, connect them through a common controller so they stage together, and check the neutral current after commissioning. If one unit fails and the other two run, the imbalance is 13 A on two phases — tolerable for a short period, not for a season.

When to pay for the upgrade

Situation Recommended
House, 5–10 kW, existing 40–63 A single phase Single phase inverter unit
Small guesthouse, 15 kW, single phase only Two 8 kW single-phase units on separate circuits, or upgrade
Factory or school with existing three-phase Three phase, always
Load above 20 kW, single phase only Upgrade; parallel single-phase units become unmanageable
Rural supply with weak voltage Three phase if available; otherwise inverter units and check voltage under load

The cost of a three-phase upgrade varies widely — from a new meter and distribution board to a new transformer for a remote site. Get the utility’s figure before the equipment is specified; the heat pump is the cheap part of that decision.

Commissioning checks that belong on the record

  • Measured voltage at the unit terminals with the compressor running, all phases.
  • Running current per phase, compared with the nameplate.
  • Phase sequence confirmed for three-phase units (a reversed phase stops the compressor or the fan).
  • Earth continuity and resistance.
  • RCD trip test, with the unit running.
  • Voltage drop measured between no-load and full load.

These six readings take twenty minutes and settle most supply-related warranty arguments before they start.

Longkang Environmental Equipment Co., Ltd. builds the same model range in both single-phase and three-phase versions up to 15 kW, so a site can start on single phase and move to three phase later without changing the unit footprint or the pipework. Phone: +86 400-878-0280 | +86 130-0200-1280

Questions from installers

Can a 380 V unit run on 220 V?

No. A three-phase compressor will not start on single phase, and attempting it destroys the motor. Some units are dual-voltage by design with a changeover kit and a different compressor; those are rare and must be specified at the factory.

What size breaker does a 10 kW heat pump need?

A 20 A motor-rated breaker for an inverter unit drawing 13–14 A. For a fixed-speed unit of the same capacity, allow 25 A and check the starting current against the supply’s fault level.

Can I share the existing 30 mA RCD with the house circuits?

Not advisable. Inverter leakage current plus a washing machine plus a bathroom circuit will cause nuisance tripping, and every trip is a hot water outage. Fit a dedicated circuit and a dedicated RCD.

Does a three-phase unit need a neutral?

Many do, for the control board and fan; some larger units use a 400 V control supply and do not. Check the wiring diagram — connecting a unit that needs a neutral without one destroys the control board within seconds.

Will a single-phase unit work on a 50 A supply with other appliances?

Yes if the total connected load stays under about 80% of the supply rating and the unit is inverter-driven. Do the sum: unit 14 A, water heater 10 A, cooker 20 A, lighting 5 A is already 49 A and leaves nothing for the rest.

How do I know if the site has three-phase power?

Look at the meter and the main switch: a three-pole main switch and a meter with three live conductors indicate three phase. Confirm with the utility before ordering, because a building wired for three phase may still have a single-phase supply contract.