- Automatic transfer to standby. Loss of a running machine must start the standby within seconds, without operator intervention.
- Load limiting on restart. Bringing four machines on at once trips the site breaker; the controller must ramp.
- BMS integration. Modbus or BACnet with per-machine status, alarms, current load and setpoint, plus remote reset of faults.
- Chilled water temperature reset. Allowing the supply temperature to float upward as the load falls saves energy and extends free cooling.
Maintenance without downtime
Design the plant so that any single machine, pump or tower cell can be isolated and serviced while the hall runs:
- Isolation valves on both the evaporator and condenser connections of every machine.
- A maintenance bypass on the header, not just on the machine.
- Space around each machine for tube bundle removal — a condenser bundle often needs 1.5 times its length in free space.
- Rigging access, because a compressor replacement in a basement plant room is a project in itself.
Frequently asked questions
Can an air-cooled chiller serve a data center?
For small halls up to a few hundred kW, yes, particularly where water is unavailable or the climate is cool. Above 500 kW, the efficiency and footprint penalty usually makes water-cooled the better choice despite the tower.
Should a data center specify magnetic bearing chillers?
Where maintenance access is difficult and the machine runs continuously, often yes: no oil, no oil changes, no oil-related failures, and better part-load efficiency. The premium is typically 30%–50%, and the payback comes from availability as much as energy.
How much redundancy is enough?
Tier III requires N+1 with concurrent maintainability; Tier IV requires 2N with fault tolerance. The right answer is set by the facility’s availability target, not by the chiller supplier — decide it before the plant layout is drawn.
Why 15/21 °C instead of 7/12 °C?
Because the servers do not need 7 °C. ASHRAE’s allowable envelope permits much warmer supply air and water, and the higher chilled water temperature improves chiller efficiency by 20%–30% and multiplies free-cooling hours. Verify with the IT equipment vendor before changing the design.
What restart time should be specified?
Ask for the time from power restoration to full cooling, including the compressor anti-recycle delay and the sequencing. A typical centrifugal needs 3–5 minutes; some designs achieve under 2 minutes with a UPS-supported control system.
How is chiller efficiency reported for a data center?
Usually as part-load efficiency at the actual operating point (often 75%–100% load, not 50%), plus the annualised PUE. Quoting only full-load COP hides the part-load behavior that dominates a 24/7 facility.
Longkang Environmental Equipment Co., Ltd. supplies water-cooled screw, centrifugal and magnetic-bearing chillers with the redundancy arrangement and restart sequence defined in the proposal, together with the part-load table at the facility’s actual load profile. Phone: +86 400-878-0280 | +86 130-0200-1280