Stage 1 — Pre-start checks (before the isolator is closed)
| Check | Acceptance | Instrument |
|---|---|---|
| Earthing | ≤ 4 Ω | Earth tester |
| Insulation resistance | ≥ 1 MΩ at 500 V | Megger |
| Supply voltage | Within ±10% of nominal | Multimeter |
| Phase sequence | Correct (scroll compressor) | Phase rotation meter |
| Control circuit | No errors on display | Controller |
| Water circuit filled and vented | No air at highest vent | Visual |
| Flow switch | Closes on pump start | Controller status |
| Crankcase heater | Energised 6–8 h before start | Clamp meter |
The crankcase heater check is the one most often skipped. If the compressor has been in a cold store or on a winter site, refrigerant has migrated into the oil. Starting without pre-heating can foam the oil, starve the bearings and score the scroll. Six hours is the minimum; overnight is better.
Stage 2 — Dry run and rotation
Run the pump only, with the compressor locked out.
- Confirm flow: pressure differential across the unit should be within 10% of the design figure.
- Confirm no air noise and a stable flow switch.
- Check for leaks at every joint, particularly the ones made on site.
- Jog the compressor for two seconds and confirm rotation direction against the arrow.
If the compressor runs backwards, stop immediately. A scroll compressor running in reverse will be damaged within a minute, and the noise is not always obvious on a large unit.
Stage 3 — First start and stabilisation
Allow 15–20 minutes of steady operation before recording anything. Water temperature, pressures and current all drift during the first minutes.
| Parameter | Typical value at 20 °C ambient, 15→45 °C water | Note |
|---|---|---|
| Suction pressure (R410A) | 8–11 bar | Rises with ambient |
| Discharge pressure | 22–28 bar | Above 30 bar indicates poor airflow or overcharge |
| Discharge temperature | 70–85 °C | Above 95 °C is a fault |
| Water ΔT across unit | 4–5 K | Above 7 K indicates low flow |
| Compressor current | Within nameplate FLA | Compare with datasheet |
| Superheat | 5–8 K | Below 3 K risks liquid return |
| Subcooling | 5–10 K | Confirms charge |
Record the ambient temperature at the same time as the readings. A unit that looks weak at 0 °C may be perfectly correct, and a unit that looks strong at 25 °C may be overcharged.
Stage 4 — Capacity verification
The practical check is a heat balance on the water side:
Capacity (kW) = flow (L/s) × 4.186 × ΔT (K)
For a 1.0 L/s flow and a 5 K rise, that is 20.9 kW. Compare with the datasheet capacity at the measured ambient and water temperature, and accept within 10%. If the measured figure is low:
| Symptom | First check | Then |
|---|---|---|
| Low ΔT and normal current | Flow too high | Reduce pump speed or rebalance |
| High ΔT and low current | Flow too low or air | Strainer, valve, vent |
| Normal ΔT, low capacity, high discharge | Airflow restriction or dirty coil | Clearances, coil cleaning |
| Normal ΔT, low capacity, normal pressures | Ambient correction misapplied | Recheck design temperature |
Stage 5 — Controls, safeties and sequences
Test each protection deliberately, because a protection that has never operated is not known to work.
| Test | Method | Expected result |
|---|---|---|
| High pressure | Block part of the coil | Cut-out at setpoint, manual reset |
| Low pressure | Close the liquid line valve briefly | Cut-out, alarm, no repeated restart |
| Flow failure | Stop the pump | Unit stops within 10 s |
| Freeze protection | Lower the setpoint below the limit | Unit stops before 2 °C water |
| Defrost | Force a defrost cycle | Completes within 10 min, water flows away |
| Power failure | Open the isolator | Clean stop, correct restart on power return |
| Remote enable | Signal from BMS | Unit follows, alarm reported |
Do not leave a forced defrost or a blocked coil test half-finished. Restore every valve and setting and record that you did.
Stage 6 — Handover
| Deliverable | Content |
|---|---|
| Commissioning sheet | All readings above, signed and dated |
| As-built drawing | Pipe routes, valve positions, sensor locations |
| Setpoint schedule | Storage temperature, differential, timers |
| Maintenance plan | Tasks, intervals, spare parts |
| Operator training | 1–2 hours, with a walk-through of alarms |
| Warranty registration | Serial numbers, start date |
Longkang Environmental Equipment Co., Ltd. provides a commissioning sheet with the unit that mirrors the tables above; returning it completed is what starts the warranty period. Phone: +86 400-878-0280 | +86 130-0200-1280
Questions from commissioning engineers
How long should commissioning take?
For a single unit with an existing water circuit, three to four hours. Add half a day if the system has multiple units, a buffer tank and BMS integration, because each sequence has to be proved separately.
Can commissioning be done in winter?
Yes, and it is often the most informative time. But the capacity check has to use the ambient correction, and defrost must be observed at least twice. Do not commission a low-temperature unit in summer and assume it will behave the same at −15 °C.
What if the measured capacity is 15% below the datasheet?
First confirm flow and ΔT with independent instruments. If both are right and the shortfall persists, check the charge and the coil condition. A persistent 15% shortfall is a warranty matter, not something to accept.
Is a nitrogen pressure test required on the refrigerant circuit?
The circuit is factory-tested and charged. A site pressure test is only needed if the refrigerant lines were opened, for example on a split system. If they were, evacuate to below 500 microns before charging.
How do I know the defrost is working properly?
Watch one complete cycle: frost should clear from the coil within 10 minutes, the water flow from the base should be steady, and the unit should return to heating without a long pause. Repeated defrosts less than 30 minutes apart indicate a sensor or airflow problem.
Should I set the storage temperature to 60 °C at commissioning?
Yes, if the system serves potable water. Set the tank to 60 °C and fit a blending valve at the outlet. Where the heat pump cannot reach 60 °C at low ambient, use an immersion heater for the final rise rather than compromising on legionella control.