Indicative equipment prices
The figures below are ex-works equipment prices for standard commercial units, 380 V, heating to 55 °C, excluding tank and installation. They are for budget planning only — a real quotation depends on the design point.
| Nominal heating capacity | Typical application | Equipment price (USD) | Hot water at 40 K rise |
|---|---|---|---|
| 10 kW | Guesthouse, 20–30 rooms | 2,500–4,200 | about 2.1 t/day |
| 20 kW | Small hotel, 40 rooms | 4,500–7,500 | about 4.3 t/day |
| 40 kW | Hotel, 80 rooms; dormitory 150 people | 8,000–13,000 | about 8.6 t/day |
| 80 kW (2 × 40) | Hotel, 150 rooms; factory 400 workers | 16,000–25,000 | about 17 t/day |
| 160 kW (4 × 40) | Resort, hospital, campus | 30,000–45,000 | about 34 t/day |
Modular banks cost slightly more per kW than a single large unit but avoid a single point of failure and simplify transport to a rooftop.
What is inside a quotation
| Line item | Share of installed cost | What to check |
|---|---|---|
| Heat pump unit(s) | 40%–50% | Capacity and COP at the design ambient, not at 7 °C |
| Storage tank | 15%–20% | Material (SUS304, SUS316L, enamel), insulation thickness, warranty |
| Pumps and valves | 8%–12% | Brand, head and flow at duty point, standby pump |
| Pipework and insulation | 8%–12% | Pipe material, insulation thickness, trace heating if outdoor |
| Control panel and sensors | 5%–8% | Controller brand, remote monitoring, number of temperature sensors |
| Installation and commissioning | 8%–15% | Crane, scaffolding, electrical works, water connections, flushing |
| Freight, duty and insurance | 3%–8% | Incoterm, port of discharge, unloading responsibility |
A quote that lists only “heat pump and accessories” cannot be compared with one that lists seven lines. Ask for the bill of quantities before comparing totals.
The eight specification choices that move the price
| Choice | Price effect | When it is worth paying |
|---|---|---|
| Cold-climate (vapor injection) | +15%–25% | Design ambient below −7 °C |
| High-temperature outlet 75–85 °C | +20%–35% | Replacing steam or pressurised hot water |
| Stainless steel 316L tank instead of 304 | +25%–40% on the tank | Chloride above 200 mg/L or aggressive water |
| Inverter-driven compressor and fans | +10%–18% | Part-load operation over 3,000 h/year |
| Duplex stainless or titanium heat exchanger | +12%–20% | Seawater, brackish water, process water |
| Remote monitoring and BMS interface | +2%–5% | Multiple sites, or a facility team without on-site HVAC staff |
| Explosion-proof or marine specification | +40%–90% | Hazardous area, offshore, coastal salt spray |
| Acoustic enclosure | +8%–15% | Unit within 15 m of bedrooms or offices |
Why two quotes for the same duty differ so much
Different design points. One supplier quotes capacity at 7 °C ambient and 15 °C inlet; another at −2 °C and 5 °C. The second machine is genuinely larger, and the price difference is real work, not margin.
Different battery limits. Is the tank included? The circulating pump? The electrical cable from the distribution board? The crane? A 30% price gap often disappears once the scope is equalised.
Different materials. A 304 tank with 50 mm insulation and a 316L tank with 80 mm are not the same product, and the price difference is mostly stainless steel.
Different redundancy. Two 40 kW units cost more than one 80 kW unit but keep the building in hot water during maintenance.
How to compare quotes properly
- Fix the design conditions in writing: ambient dry-bulb and relative humidity, cold water temperature, outlet temperature, daily volume, peak-hour demand.
- Require a capacity table at four ambient temperatures for every model offered.
- Require the bill of quantities with brands for pumps, valves, controller and tank material.
- Require the warranty terms per component — unit, compressor, tank, controls — separately.
- Normalise freight and installation: state the Incoterm and who unloads, who wires, who commissions.
Frequently asked questions
Why is one quote half the price of another?
Usually three reasons combined: a smaller machine rated at a warmer design point, a scope that excludes tank or installation, and thinner materials. Occasionally it is a genuinely lower-cost supply chain. The way to tell is to equalise the design point and the bill of quantities, then compare.
Is a cheaper unit a false economy?
It can be. The compressor and the coil are where cost is removed first. A unit that loses 15% of its COP over eight years costs more in electricity than the price difference, particularly in a hotel running 4,000 hours a year.
What is typically not included in an equipment price?
Storage tank, circulating pumps, pipework and insulation, electrical supply to the unit, foundations and crane, water treatment, and commissioning labor. In retrofit projects, removing the old boiler is also usually excluded.
What are typical payment and delivery terms?
Common terms are 30% deposit with order, 60% before shipment, 10% after commissioning, with 25–45 days production for standard models and 45–60 days for cold-climate or high-temperature units. Confirm the Incoterm and the port before comparing prices from different countries.
Does the tank or the heat pump dominate the cost?
For a small system the unit dominates. Above about 20 t/day of storage the tank becomes the larger line item, which is why tank material and insulation specification deserve as much attention as the compressor brand.
How much should I budget for spares?
Allow 2%–3% of equipment cost per year for filters, sensors, contactors and refrigerant, plus a set of compressor spares for critical sites. A spare controller and a spare fan motor on the shelf remove most of the downtime risk.
Longkang Environmental Equipment Co., Ltd. quotes with the design point, the capacity table and a seven-line bill of quantities attached, so two offers can be compared line by line rather than by total. Phone: +86 400-878-0280 | +86 130-0200-1280