Before the first load
| Check | Acceptance | Instrument |
|---|---|---|
| Chamber and ductwork sealed | No visible leak, door gaskets compressed | Smoke test or hand test |
| Fan rotation | Correct, airflow in the design direction | Anemometer |
| Compressor crankcase heater | 8 h minimum before start | Clamp meter |
| Condensate drain | Flows to the tank, trap working | Water test |
| Sensors | Within 1 K of a reference | Calibrated thermometer |
| Interlocks | All operate | Simulation |
| Emergency stop | Stops all motion | Physical test |
| Odor system | Fan running, media in place | Visual |
A chamber that leaks air cannot be commissioned: the humidity control loop will hunt and the energy figure will be meaningless. Spend the time on the seals.
Stage 1 — Empty run and heat-up
- Run the fans for 30 minutes and measure the airflow at the design points.
- Start the compressor and allow the chamber to reach the setpoint with no load.
- Record the heat-up time and the steady-state temperature stability.
| Parameter | Target | If outside |
|---|---|---|
| Heat-up to 55 °C | 20–40 min | Insulation, door seals, capacity |
| Temperature stability at no load | ±2 K | Control tuning, sensor position |
| Fan current | Within nameplate | Belt tension, blockage |
| Compressor current | Below FLA | Charge, airflow |
| Chamber differential pressure | −20 to −50 Pa | Extract fan setting |
Stage 2 — Load ramp
Feed in steps, not all at once. Each step should stabilise before the next.
| Step | Feed rate | Hold time | Watch |
|---|---|---|---|
| 1 | 30% of design | 45 min | Inlet blockage, belt tracking |
| 2 | 50% | 60 min | Temperature recovery, condensate flow |
| 3 | 75% | 60 min | Humidity control, product moisture |
| 4 | 100% | 120 min | Energy, discharge moisture, dust |
At each step record the chamber temperature, exhaust humidity, feed rate, product moisture, condensate flow and power. These five values tell you whether the machine is doing what the datasheet says.
Stage 3 — Moisture and throughput test
| Measurement | Method | Acceptance |
|---|---|---|
| Inlet moisture | Oven dry at 105 °C, triplicate sample | Within 2 points of design |
| Outlet moisture | Same method, three samples across the run | Target ±3 points |
| Throughput | Weigh inlet cake over 2 h | At least 95% of design |
| Evaporation | Mass balance | Within 5% of calculated |
| Product temperature | At discharge | Below 45 °C unless specified |
Take samples properly: a grab sample from the top of a skip is not representative. Sample the discharge stream across its full width, at three times during the run, and composite them.
Stage 4 — Specific energy
Specific energy (kWh per tonne of water) = power (kW) × hours ÷ water evaporated (t)
For a heat-pump dryer, 300–400 kWh per tonne of water is a realistic range at moderate ambient; thermal dryers use 800–1,200.
| Reading | Good | Investigate |
|---|---|---|
| Specific energy | 300–400 kWh/t | Above 450 kWh/t |
| Compressor share | 60%–75% of total | Above 80% suggests fan or seal losses |
| Ambient correction | Note the ambient | Cold ambient raises the figure |
Measure power with a kWh meter over at least two hours at steady load. Instantaneous readings from a panel ammeter are not a measurement; they are an indication.
Stage 5 — Emissions and housekeeping
| Item | Acceptance |
|---|---|
| Odor at the boundary | Within the site’s permit or agreed limit |
| Visible dust at transfer points | None |
| Condensate quality | Within the discharge consent, or routed to treatment |
| Condensate leak | None |
| Noise at 1 m | Per datasheet, typically below 85 dB(A) |
| Floor condition | Dry, no spillage |
Stage 6 — Handover package
| Document | Content |
|---|---|
| Commissioning record | All readings above, signed |
| Moisture and mass balance | Sample results and calculations |
| Setpoint schedule | Temperature, humidity, feed rate, alarms |
| Maintenance plan | Tasks and intervals |
| Operator training | 2–4 hours, including a blockage drill |
| Spare parts list | Recommended first-year holding |
Longkang Environmental Equipment Co., Ltd. requires the moisture and mass balance sheets to be completed and returned before the performance guarantee is confirmed, because those two documents are the only objective record of what the plant achieved on site. Phone: +86 400-878-0280 | +86 130-0200-1280
Questions from commissioning teams
How long does commissioning take?
Three to five days for a single unit: one day of checks, one day of heat-up and load ramp, two days of moisture and energy testing, and half a day for training and handover. Cold weather adds time.
Can commissioning be done with the plant’s normal sludge?
It should be. A test on a synthetic sample proves nothing about the plant’s real material, and the moisture and polymer content both affect drying.
What if the outlet moisture is 5 points above target?
First extend the residence time by reducing the feed rate. If the moisture falls, the machine is at its capacity limit, and the specification or the feed rate has to change. If it does not fall, the problem is airflow, humidity control or a seal leak.
How is the evaporation rate verified?
By mass balance: wet mass in minus dry mass out, divided by the run time. It should agree with the condensate volume within about 10%, since most of the evaporated water leaves as condensate.
Is the energy figure measured at the panel or at the meter?
At a dedicated kWh meter on the dryer supply, including fans, compressor and controls. Measuring only the compressor understates the figure and flatters the result.
What ambient temperature should the test be corrected to?
The datasheet condition, usually 20 °C. If commissioning happens at 5 °C, the specific energy will be higher and the capacity lower; record the ambient and correct rather than declaring a failure.