Diversity: the number that decides the plant size
The sum of every tenant’s peak is not the building’s peak. Tenants peak at different times, and the diversity factor converts one into the other.
| Building type | Diversity factor | Note |
|---|---|---|
| Shopping mall, retail only | 0.75–0.85 | Similar hours, similar peaks |
| Mall with cinema and food court | 0.65–0.80 | Different peaks, evening load |
| Office and retail mixed | 0.60–0.75 | Office day, retail evening |
| Mixed use with hotel | 0.55–0.70 | Hotel is 24-hour, others are not |
| Complex with data center | 0.70–0.85 | Data center is constant |
Applying 0.7 to a 10,000 kW sum gives a 7,000 kW plant. Getting the factor wrong in either direction is expensive: too high and the plant never loads; too low and the mall is hot on a Saturday in August.
The load duration curve matters more than the peak
| Load band | Share of annual hours | Chiller behavior |
|---|---|---|
| 80%–100% | 8%–12% | All machines running |
| 60%–80% | 20%–25% | Most machines running |
| 40%–60% | 30%–35% | Staging decisions |
| 20%–40% | 25%–30% | One or two machines |
| Below 20% | 8%–12% | One machine, part load |
Most of the year is spent between 20% and 60%. A plant designed only for the peak will be inefficient for 80% of its running hours.
Machine selection for a complex
| Configuration | Peak | Part load | Comment |
|---|---|---|---|
| 3 × 33% centrifugal | Good | Poor below 40% | Cheap per kW, poor turndown |
| 4 × 25% screw | Good | Good | Common choice |
| 2 × 40% + 2 × 10% | Good | Excellent | Strongest part load, more machines |
| 6 × 17% modular | Good | Excellent | High footprint |
| 2 large + 1 small | Good | Good | Simple, needs cross-connection |
For a 7,000 kW plant, four 1,750 kW screw machines with VSD, plus a 700 kW machine for night load, covers the range without surging and keeps the plant efficient at 15%.
Hydraulics: primary/secondary with multiple plant rooms
| Arrangement | Suited to | Watch out for |
|---|---|---|
| Central plant, primary/secondary | Single plant room | Decoupler and header sizing |
| Distributed plant per building | Large sites | Diversity between plants |
| Central plant plus satellite | Phased development | Communication and control |
| Variable primary flow | Single chiller bank | Minimum flow protection |
Large complexes often have a central plant and satellite plants for outlying buildings. The control system has to stage them together, or the satellites will fight the central plant.
Thermal storage: shifting the peak
| Storage type | Capacity | Discharge | Comment |
|---|---|---|---|
| Chilled water tank | 8–12 kWh/m³ | Slow | Cheap per m³, large footprint |
| Ice storage | 50–60 kWh/m³ | Fast | Compact, lower chiller efficiency |
| Phase change material | 40–50 kWh/m³ | Medium | Modular, higher cost |
A mall with a 7,000 kW peak and a 4,000 kW night load can shift 2,000–3,000 kW of peak to night with ice storage. Whether that pays depends on the tariff difference between day and night, which in many markets is 2:1 or more.
Tenant metering and billing
| Method | Accuracy | Cost | Comment |
|---|---|---|---|
| BTU meter per tenant | High | Medium | Standard for new build |
| Sub-meter on fan coil | Medium | Low | Approximate |
| Area allocation | Low | Lowest | Disputes |
| Run-time allocation | Low | Low | Ignores load |
A complex without tenant metering has no way to bill cooling fairly, and no incentive for tenants to run efficiently. BTU meters on each tenant’s branch, read by the BMS, are the normal solution.
| Metering point | Purpose |
|---|---|
| Chiller plant | Total production and efficiency |
| Each building riser | Landlord area vs tenant area |
| Each tenant branch | Billing |
| Each major plant item | Maintenance and diagnosis |
Staging and control
| Function | Requirement |
|---|---|
| Staging | On load and leaving water temperature, with a time delay |
| Sequencing | Rotate lead machine weekly |
| Chilled water reset | Raise supply temperature at low load, within humidity limits |
| Condenser optimization | Tower fan staging against condenser water temperature |
| Tenant scheduling | Unoccupied setback per tenant |
| Alarm escalation | To the building operator, then to the service provider |
The condenser water optimization is often worth more than the chiller staging: running the tower fans harder to lower the condensing temperature by 2 K improves chiller efficiency by 3%–5%, and the fans cost far less than the compressor.
Noise, plume and roofspace
| Issue | Measure |
|---|---|
| Tower noise to residences | Low-noise fan, acoustic barrier, setback |
| Plume visible from apartments | Hybrid tower, or relocate |
| Roofspace competition with solar | Coordinate layouts |
| Vibration into retail below | Spring isolators, floating bases |
| Access for maintenance | Crane access, roof hatches |
A mall roof is a contested space: towers, solar panels, rooftop units, signage. The tower layout should be fixed before the solar array, because the tower needs clean air and cannot be shadowed or surrounded.
A configuration example
A 90,000 m² mall with cinema and food court, 8,500 kW sum of tenants, diversity 0.75:
| Item | Selection | Reason |
|---|---|---|
| Design load | 8,500 × 0.75 | 6,375 kW |
| Chillers | 4 × 1,400 kW screw VSD | Staging, part load |
| Night machine | 1 × 500 kW | Low load efficiency |
| Storage | 1,500 kWh ice | Peak shaving |
| Towers | 4 cells, 25% each | Turndown |
| Hydraulics | Primary/secondary | Variable tenant flow |
| Metering | BTU per tenant | Billing |
| Control | BMS with tenant scheduling | Energy management |
The night machine is the item most often omitted and most often regretted: without it, the plant runs a 1,400 kW machine at 10% load every night for years.
Longkang Environmental Equipment Co., Ltd. configures complex plants with the load duration curve, the staging logic and the metering points defined together, because a plant that cannot be measured cannot be managed. Phone: +86 400-878-0280 | +86 130-0200-1280
Questions from MEP designers
What diversity factor should I use?
0.65–0.85 depending on the tenant mix. Model the peaks by tenant type rather than applying a single factor to the total; a cinema and an office do not peak together.
How many chillers should a large plant have?
Four to six is the practical range: enough for staging and redundancy, not so many that the plant room and the control system become unmanageable.
Is ice storage worth it?
Where the day-night tariff ratio exceeds about 2:1 and the building has space for the tanks. It also reduces the electrical peak, which matters where capacity charges are high.
How do I bill tenants fairly?
BTU meters on each tenant branch, with a standing charge for the plant capacity and a consumption charge for the energy. Publish the method in the lease.
Can the plant be phased with the development?
Yes, and it should be: design the plant room and headers for the final build, install chillers as phases open, and keep the staging logic modular. Oversizing the first phase wastes capital.
What is the biggest efficiency mistake in a mall plant?
Running a large machine at low load at night, and not resetting the chilled water temperature. Both are control issues, not equipment issues.