“How long does a heat-pump system take to install?” has no single answer, but it has a structure. A small project of two to four units and one tank normally takes 10–15 days; a medium project of six to ten units with multiple tanks and terminal work takes 20–30 days; a large project of more than ten units across buildings takes 45–60 days. The difference is not the number of units. It is the handover of the civil works, the power connection and the pipe route.
The schedule becomes controllable when it is broken into six stages, each with a scope, a duration and a predecessor. The critical path is usually only two items: foundation curing and pipe pressure testing.
1. Six stages and their predecessors
| Stage | Scope | Typical duration | Predecessor |
|---|---|---|---|
| 1. Survey and detailed design | Site measurement, load check, pipe route, drawings | 3–7 days | Architectural and structural drawings |
| 2. Foundation and civil works | Base, waterproofing, embedment, curing | 5–10 days | Design confirmed, site handed over |
| 3. Delivery and lifting | Delivery, lifting, leveling, fixing | 1–2 days | Access route, lifting plan |
| 4. Piping | Water pipes, valves, supports, insulation, pressure test | 5–8 days | Foundation cured, pipe on site |
| 5. Electrical and controls | Cable, panel, grounding, wiring | 3–5 days | Power available, panel on site |
| 6. Commissioning | Flush, fill, vent, set points, trial run | 2–3 days | Water, power and controls complete |
The six stages add to 19–35 days, but actual projects often take 30–50 days. The extra time is spent waiting: for civil handover, for the power application, for another trade to release a pipe route. The two stages that cannot be compressed are the concrete cure (3–7 days) and the pressure test and observation. The rest can overlap: piping and electrical can run together, and the control panel can be prefabricated and installed on arrival.
2. The survey is the cheapest correction window
The survey and detailed design take only 3–7 days, but they catch the errors that are expensive later. Confirm five things:
Roof or floor load. A 10 kW unit weighs about 300–400 kg in operation; a 5 m³ tank adds 5 t of water. A light-steel roof needs a structural check. A steel beam added before construction costs a few thousand CNY; a new foundation after installation costs far more.
Transport and lifting route. Measure the unit dimensions, the turning radius, the lift capacity and the crane position. A unit that cannot pass the stair corner may require removing a wall, adding two weeks.
Pipe route and clashes. Hot water, return, make-up and cable tray must be checked against fire, gas and drainage lines at the drawing stage. A site change often means removing installed supports.
Power position and capacity. Check the total power, starting current, spare capacity in the distribution board and cable length. If the capacity is short, the utility application takes weeks; this is the most commonly missed item.
Drainage. Defrost water, safety-valve discharge and tank overflow need an organized route. They cannot be left to run over the roof waterproofing.
3. Winter construction: two things not to do
Do not pressure-test with water below 0 °C. Ice expansion can split fittings and heat exchangers. Use an air test at the reduced pressure allowed by the code, with proper safety measures, or pressure-test with water and immediately blow dry with compressed air and add antifreeze. For a northern project starting after November, plan this before mobilization.
Do not pour concrete in freezing weather without protection. Concrete that freezes before setting loses strength permanently. Use an antifreeze admixture, cover and cure for 7–10 days. This adds about five days to the schedule; leave room for it.
Commissioning also has a low-temperature limit. Some models cannot start in heating below −5 °C. Schedule commissioning for the warmer part of the day, or use the electric backup to raise the water to 10 °C before starting the heat pump.
4. Three inspections, not one
First: concealed works. Before insulation is applied, inspect the pressure test, support spacing, slope and valve orientation. Test at 1.5 times the working pressure and not less than 0.6 MPa, hold 10 minutes with no leak, then reduce to working pressure and hold 60 minutes. If this stage is missed, a later leak means removing the insulation.
Second: individual unit run. Start each unit and check rotation, current, noise, outlet temperature and protection. Three items matter most: fan rotation, because reverse rotation reduces airflow sharply; compressor current, which must be within the nameplate range; and the flow switch, which should stop the unit within 30 seconds when flow is lost.
Third: system run. Run all units, pumps, tanks and controls together for 72 hours. This tests the system, not the unit: whether the water temperature holds, whether unit rotation works, whether makeup water keeps up at peak demand and whether the system changes over on a fault.
| Acceptance item | Method | Criterion |
|---|---|---|
| Pressure test | 1.5× working pressure, 10 min | No leak, no pressure drop |
| Insulation | Thickness, tap test, visual | Design thickness, no voids, sealed joints |
| Electrical insulation | Megger | ≥ 0.5 MΩ |
| Earth resistance | Earth tester | ≤ 4 Ω |
| Outlet temperature | Calibrated thermometer | Design ±2 K |
| Continuous run | 72 h record | No fault stop |
The 72-hour run is often skipped because the building is still under fit-out and the water load is low. A workable compromise is to accumulate 72 hours in blocks, provided at least one block covers the morning or evening peak. Without it, system-level faults appear only after occupancy.
5. Five common delays
Civil handover. Roof waterproofing incomplete or the mechanical room uncleaned; the installation team waits. Usually one to two weeks.
Equipment delivery. Non-standard tanks, special-voltage units and integrated control panels often take 20–40 days. Put the delivery date and liquidated damages in the contract.
Power not connected. The application, upgrade and cable work take weeks and are outside the contractor’s control. Start the application at contract signature, not when the unit arrives.
Pipe clashes. Site changes in route or elevation take little material but much time, and leave hidden risks.
Notification and access. A dormitory or factory needs notice for shutdowns and access. A late notice can stop work for days even when the equipment is ready.
Putting the schedule into the contract
A schedule becomes enforceable only when each milestone has a date, a payment and an evidence document. “About 30 days” is not a schedule; a signed milestone table is.
| Milestone | Payment share | Evidence | Delay trigger |
|---|---|---|---|
| Equipment arrival | 20–30% | Delivery note and inspection record | Supplier delivery date missed |
| Concealed works accepted | 20% | Pressure-test record, support and slope check | Civil handover late or pipe route changed |
| System commissioning | 30% | 72-hour run record, set points, alarm list | Power not connected or water load unavailable |
| Final acceptance | 15–20% | As-built drawings, O&M manual, spare list | Documents incomplete |
| 30-day revisit | 5–10% retention | Full-load performance record | Seasonal load not available |
Write the extension conditions next to the milestones: site not handed over, power not connected, design change, abnormal weather or force majeure. Each extension needs a written notice within a stated number of days; a verbal instruction is not evidence at final account. The same clause should state who pays for remobilization after a delay caused by another trade.
Keep one distinction clear: commissioning is not handover. A system can pass a 72-hour run in a building that is still half occupied and then fail in the first real peak. The 30-day revisit is the bridge. It checks the plant at real load, confirms the staging and storage behavior, and gives the owner a defined window to have defects corrected before retention is released. Longcom’s air-source heat pump page provides the model data needed to write those acceptance figures into the contract.
Common questions
How long for a small system?
Typically 10–15 days for two to four units and one tank, if the civil works and power are ready. The range excludes delivery lead time.
Can the schedule be shortened?
Only by overlapping stages and preparing the front-end works. Foundation cure and pressure testing cannot be compressed safely.
Why inspect before insulation?
Because the pressure test and support spacing are hidden afterward. A leak found after insulation means removing and replacing it.
Is a 72-hour run always possible?
Not always. Accumulate 72 hours in blocks and include at least one peak-demand period. A run at low load does not prove the system.
Can we pressure-test with water in winter?
Not below 0 °C without protection. Use air testing or water testing followed by immediate blow-dry and antifreeze.
What is the most common delay?
Civil handover and power connection, not the heat pump. Both are outside the equipment supplier’s control and must be scheduled first.
What are the stages?
Foundation, piping, electrical, commissioning and handover. Each has a check. A skipped stage shows up at the first winter.
What must the acceptance test prove?
Capacity, COP, flow, safety interlocks and the document set. Run at the design condition, record the data and sign it. A test at a favorable ambient proves little.
Further technical reading
- Heat-Pump Commissioning Checklist
- Heat-Pump Acceptance Standards
- Air-Source Heat Pump Installation
- Heat-Pump Electrical Wiring and Control Panels
LONGCOM can provide the six-stage schedule, the survey checklist and the three inspection records for a heat-pump project. For an installation program review, contact 400-878-0280 or 13002001280.
Related reading
Heat-pump commissioning · Heat-pump water piping · Service access clearance