Data-center chiller savings are rarely decided by the chiller alone. The load runs for 8,760 hours a year, and the annual load-duration curve matters more than a single rated efficiency point. A plant that is excellent at full load but poor at 60% will lose to a plant with a flatter part-load curve.
This case is a planning study based on public tender parameters for a medium-sized data center: 1,200 racks at 6 kW each, a design cooling load of 6,800 kW, and an existing plant of three 800 RT fixed-speed centrifugal chillers plus one standby. The numbers are a worked example, not a claim about a specific operating site. The purpose is to show where the savings come from and how they are verified.
Start with the load-duration curve
The first step is not equipment selection; it is splitting the year into load bands. A data center has a high base load with a modest day-time lift from offices and test areas. The table uses 8,760 hours and a design load of 6,800 kW.
| Period | Hours | Average load | Cooling load | Chillers running |
|---|---|---|---|---|
| Cooling-season weekday, 08:00–20:00 | 1,560 | 92% | 6,256 kW | 3 |
| Cooling-season nights and weekends | 2,880 | 78% | 5,304 kW | 2 |
| Shoulder season | 2,460 | 68% | 4,624 kW | 2 |
| Winter, including free cooling | 1,860 | 62% | 4,216 kW | 1 plus plate heat exchanger |
More than half the year sits between 62% and 78% load. A fixed-speed centrifugal chiller in that band may run at about 70% of its rated efficiency. The winter block also offers 1,860 hours of plate free cooling, with mechanical cooling only as trim.
The existing plant uses 10.82 GWh a year, or about 236 kWh/m² of machine-room area, with a plant efficiency ratio of 3.9. That was respectable a decade ago; today it leaves more than 40% of savings on the table.
Three changes, not one
The study combines three measures, each solving a different problem.
Magnetic-bearing variable-speed centrifugal chillers. Four 800 RT units, three duty and one standby. The reason is part-load performance: a magnetic-bearing machine can achieve an efficiency ratio above 9 in the 30–50% band, while a conventional variable-speed centrifugal may be around 6.5. For a data center that spends half the year in that band, the difference reaches the electricity bill.
Raise the chilled-water supply from 7/12 °C to 15/21 °C. The racks use in-row or rear-door cooling, so the terminal temperature difference is large enough for warmer water. Each 1 K increase in supply temperature improves centrifugal efficiency by roughly 3%; a move from 7 to 15 °C is about 24%. This measure does not require new chillers, but it does require terminal selection and control changes. It is often left out because the chiller schedule is already fixed.
Add plate free cooling. The plate heat exchanger switches in when the wet-bulb temperature is below 12 °C, giving 1,860 hours a year. A plate exchanger uses about one-third of the roof area of a dry cooler, which matters in a dense data center.
| Item | Existing | Study design | Change |
|---|---|---|---|
| Chillers | 3 × 800 RT fixed-speed centrifugal | 4 × 800 RT magnetic-bearing variable-speed | One added standby |
| Chilled-water temperature | 7/12 °C | 15/21 °C | 5 K to 6 K difference |
| Chilled-water flow | 1,170 m³/h | 975 m³/h | 17% lower |
| Free cooling | None | Plate exchanger, 1,860 h/year | New |
| Annual plant energy | 10.82 GWh | 7.42 GWh | 31.4% lower |
| Plant efficiency ratio | 3.9 | 5.7 | 46% higher |
The flow reduction is easy to miss. With the same cooling load and a wider temperature difference, flow falls 17%; pipe friction falls with the square of flow, and pump energy falls by about 31%. Pumps are not the headline, but they are a substantial annual load.
Part-load free cooling
Many free-cooling systems run far fewer hours than designed because the changeover is set too conservatively: the wet-bulb must be 3 K below the chilled-water return before the plate exchanger is allowed in. In a humid climate that may happen for only a few hundred hours.
The study uses partial free cooling. The plate exchanger is in series and pre-cools the return; the chiller trims the remaining difference. The changeover can then move from 9 °C to 14 °C wet-bulb, and available hours rise from about 620 to 1,860.
| Wet-bulb temperature | Plate pre-cooling | Chiller duty | Mode |
|---|---|---|---|
| ≥ 20 °C | 0 | 6,800 kW | Mechanical only |
| 16 °C | 1,360 kW | 5,440 kW | 20% pre-cool |
| 12 °C | 3,400 kW | 3,400 kW | 50% pre-cool |
| 8 °C | 5,780 kW | 1,020 kW | 85% pre-cool |
| ≤ 6 °C | 6,800 kW | 0 | Full free cooling |
The plate exchanger must be protected against open cooling-tower water. Without filtration and chemical dosing, a 0.5 mm scale layer can cut heat transfer by 15% within six months. The study includes side-stream filtration and automatic dosing, about CNY 180,000, outside the chiller package.
Capex and two paybacks
The installed cost is about CNY 15.38 million: CNY 11.20 million for four magnetic-bearing chillers, CNY 1.86 million for the plate exchanger and piping, CNY 0.62 million for pump variable-speed drives, CNY 0.74 million for controls and staging, and CNY 0.96 million for installation and removal.
The plant saves 3.40 GWh a year. At CNY 0.70/kWh, that is CNY 2.38 million a year, a simple payback of 6.5 years. On electricity alone, that is a modest case for a data center.
The second benefit is capacity. The plant efficiency ratio rises from 3.9 to 5.7 and PUE falls from 1.42 to 1.31. At a 6,800 kW IT load, the saved electrical capacity is about 570 kW, which can support more racks without increasing the total supply. At local rack-rental values, that capacity is worth more than CNY 0.90 million a year. Include it and the payback shortens to 4.7 years. The two benefits should be shown separately, because the capacity value depends on occupancy.
Verify with a regression baseline
Comparing two months of bills before and after a retrofit proves nothing: the weather and the load are different. The study uses three rules.
Build a regression baseline. Use 12 months of hourly data and regress plant power against wet-bulb temperature and IT load. After the retrofit, calculate the “should-use” power from the same variables and subtract the measured value.
Keep measurement points independent. Give the plant its own meter, separate from lighting and UPS. Meter chillers, pumps and cooling towers separately so a shortfall can be located.
Measure a full year. A data center ramps in its first year, so the first 12 months may not represent normal operation. If time is short, use three months with a documented seasonal correction.
Boundaries
The configuration does not apply to every data center. Racks above 15 kW often use cold-plate liquid cooling or immersion, where the chilled-water temperature can be 30 °C or higher. Sites with an annual wet-bulb above 22 °C may have fewer than 300 free-cooling hours, so the plate exchanger may not pay back. Old machine rooms designed for 7/12 °C may have terminal coils that cannot deliver the room condition at 15 °C. And a plant with a chilled-water storage tank designed for a 5 K difference must re-check its storage capacity at 6 K.
Common questions
How much more does a magnetic-bearing chiller cost?
At equal capacity, the chiller itself is typically 1.5–1.7 times a fixed-speed centrifugal, or 20–30% above a conventional variable-speed centrifugal. The premium is recovered through part-load efficiency and oil-free maintenance if the load profile spends enough hours in the efficient band.
Why can data-center water be 15 °C?
Because the terminals are in-row or rear-door units with a large temperature difference, not conventional fan coils. The room can still be maintained at about 24 °C. The terminal selection must be changed with the water temperature; changing only the chiller will cause condensation or a supply-air shortfall.
Does a plate exchanger reduce reliability?
It adds a bypass path, but the plate and the chiller are parallel, and the chiller starts if the plate fails. The changeover valve should fail safe to the chiller position on loss of power.
How is the plant efficiency ratio of 5.7 calculated?
Annual cooling delivered divided by annual plant electricity, including chillers, chilled-water pumps, condenser-water pumps and cooling towers, but excluding terminal fans. At 6,800 kW and 7.42 GWh, the annual cooling is about 42.3 GWh, giving 5.7.
Can the retrofit be done without shutting the data center?
Yes, in two stages: install the new chillers and plate exchanger on a new header, then cut over one existing machine at a time. Keep a temporary cooling source or use a low-load night window; a single machine changeover may take about four hours.
Is the 4.7-year payback credible?
It includes capacity value. On electricity alone the payback is 6.5 years. If the released capacity is not rented, or the rack price is low, the shorter figure will not be realized. Present both cases to the investment committee.
Why magnetic bearings in a retrofit?
They remove oil and mechanical losses at part load, reduce maintenance and allow a higher-speed, compact compressor. The saving is largest when the plant runs at part load for many hours. The retrofit must also fix the water temperatures and free cooling.
How do I verify the savings?
Use a regression baseline on the existing plant, normalize for weather and load, and compare after the retrofit. A single before-and-after reading is not evidence. Meter the chiller plant for at least a full cooling season.
Further technical reading
For the technology, see Data Center Chiller Plant: Magnetic Bearings, N+1 and High-Temperature Water. For the principle, see Magnetic-Bearing Centrifugal Chillers. For staging, see Chiller Plant Group Control. For the financial method, see Chiller Retrofit Payback.
Related reading
Magnetic-bearing chiller · Magnetic centrifugal chiller · Chiller retrofit payback