Pharmaceutical Cleanroom: An 860 kW Chiller Case

The difficult part of a pharmaceutical cleanroom chiller scheme is not the total cooling load. It is the combination of a high fresh-air fraction, tight humidity control and a production process that cannot stop for maintenance. A plant that is merely large enough will fail one of those three conditions.

This case is a planning study for an 8,000 m² solid-dosage facility with 3,000 m² of clean space, mainly Grade D with local Grade C. The area, load and equipment schedule are illustrative values for a scheme-stage calculation, not a record of a specific project.

The load is not the hard part

The study starts with a design cooling load of 860 kW at 35 °C dry-bulb and 60% relative humidity outside. The breakdown is more informative than the total.

Load item Cooling load Share Basis
Fabric 180 kW 21% Wall and roof heat gain; cleanroom insulation is good
Process equipment 260 kW 30% Granulation, tableting and coating
Fresh air 213 kW 25% 16,000 m³/h from 35 °C to 25 °C
People and lighting 100 kW 12% 150 people plus cleanroom lighting
Reheat and distribution 107 kW 12% Reheat, fan gain and duct loss
Total 860 kW 100% Before a 10% margin

Fresh air is a quarter of the load. A normal office may run at 10–15% outdoor air; a cleanroom needs 30–40% to maintain positive pressure, remove dust and dilute solvents.

The air volume is the largest of three requirements: 40 m³/h per person for 150 people is 6,000 m³/h; process exhaust for dust, humidity and solvent control is 8,000 m³/h; positive-pressure leakage is about 2,000 m³/h. The sum is 16,000 m³/h, which produces the 213 kW fresh-air load. The pressure regime is normally at least 10 Pa from clean to non-clean space and at least 5 Pa between different clean grades. The pressure difference is maintained by the fresh-air/exhaust margin, so the fresh-air load cannot be cut without changing the pressure strategy.

Why three 450 kW, not two 800 kW

At 860 kW, several configurations are nominally adequate. Two 450 kW units with one duty and one standby give only 450 kW, which is not enough. Three 450 kW units with two duty and one standby give 900 kW. Two 800 kW units with one duty and one standby give 800 kW, slightly short of the load.

The three-unit arrangement wins for three reasons. First, part-load match: at night or at weekends the cleanroom may fall below 40% load, where a 450 kW screw can still run stably. An 800 kW machine at the same load is near its minimum and may surge or cycle. Second, maintenance without a shutdown: with two duty and one standby, one machine can be serviced while two remain available. A two-machine arrangement loses half the capacity during service, and the cleanroom humidity will drift. Third, transport: a 450 kW screw is smaller and lighter, which matters in an existing building with a low door or a small lift.

Equipment Specification Quantity Arrangement
Chiller 450 kW screw 3 Two duty, one standby
Chilled-water pump 18.5 kW, 148 m³/h 3 Two duty, one standby, variable speed
Condenser-water pump 18.5 kW, 177 m³/h 3 Two duty, one standby
Cooling tower 200 m³/h 2 One duty, one standby
Desiccant rotor 8,000 m³/h 1 Local low-humidity area
Air-handling unit 16,000 m³/h 4 Zoned by clean area

Chilled water is designed at 7/12 °C. At 860 kW, the flow is 860 × 0.172 = 148 m³/h, which gives a DN200 main at about 1.31 m/s. Condenser water at 37/32 °C and 1.2 times the condenser load is 177 m³/h, also DN200 at about 1.56 m/s.

One item is often left out: chilled-water storage. During a utility changeover or a chiller restart, the chilled-water flow stops for a few minutes; the cleanroom temperature can rise 2–3 K within five minutes, and a tablet batch may be rejected. A 15-minute storage volume at 6 K is about 215 kWh, or 31 m³; the study uses a 30 m³ tank connected in parallel to the main.

Low humidity: rotor or 5 °C water

Some solid-dosage products need below 45% relative humidity, and some need 30%. At 7 °C chilled water, the apparatus dew point is about 12 °C, which gives a supply relative humidity near 60%. Chilled water alone cannot reach 45%.

Two routes are available. Cool the water to 5 °C, lower the dew point to 9 °C, then reheat the supply to 22 °C; this reaches about 40% RH but cuts chiller efficiency by 5–7% and wastes the reheat. Or use a desiccant rotor: the chilled water removes sensible heat, the rotor removes latent heat, and the regeneration temperature is about 120 °C. A rotor can reach a dew point of −20 °C and is easy to control, but it needs 8–12 kW of regeneration heat per 1,000 m³/h.

The study chooses a rotor because the low-humidity area is only 15% of the clean space. Treating 8,000 m³/h of local fresh air is cheaper than dropping the whole system to 5 °C. If the low-humidity area exceeds 40%, a central low-temperature chilled-water system may be the better route. The rotor should use steam or electricity for regeneration, not condenser heat at 40–45 °C, which is below the 120 °C requirement.

GMP piping details

Chilled water does not touch the product, but the piping still has cleanroom requirements. Use stainless steel or internally coated carbon steel; bare carbon steel will send rust into terminal coils within three years. Slope the pipe at 0.003, provide a drain at the low point, and keep branch lengths within six pipe diameters to avoid dead legs. Insulation must be covered with a metal jacket and sealed at joints; bare glass-fiber insulation is not acceptable in a clean area. Supports in the mechanical room and clean zone should be galvanized and coated, with sleeves and sealant where pipes pass through panels.

Acceptance in three records

The first record is air volume and pressure. Measure supply, return and fresh air for each zone; the deviation should be within 10% of design, and the pressure difference between adjacent grades at least 5 Pa. This follows the ventilation and air-conditioning acceptance code GB 50243-2016.

The second is temperature and humidity stability. Record 72 hours continuously; temperature should stay within ±1 K and relative humidity within ±5%, then repeat at the worst condition of high summer and full production.

The third is plant performance. Measure cooling and input power at 50%, 75% and 100% load; the efficiency should be within 5% of the approved curve. This record is often skipped, yet it sets the energy baseline for the life of the plant.

Boundaries

The scheme does not apply to a warehouse with a small clean zone: if the fresh-air fraction falls below 15%, the load profile changes and two chillers may be enough. A site with a stable industrial heat source may prefer an absorption chiller, provided the steam or hot water is reliable and the maintenance team can support it. A dry northern climate may not need a rotor, but winter humidification must be designed.

Common questions

What cooling load should a cleanroom use at scheme stage?

For a solid-dosage plant, about 100–130 W/m² of gross building area, or 250–320 W/m² of clean area. These are scheme-stage figures; the construction design must calculate each item.

Why is fresh air such a large share?

Because the cleanroom needs fresh air for positive pressure, exhaust make-up and contaminant dilution. At 16,000 m³/h and a 40 kJ/kg enthalpy difference, the load is about 213 kW, or a quarter of the total.

Is N+1 always required?

Pharmaceutical production normally requires N+1 so that a chiller failure does not cause a temperature or humidity excursion. If two independent buildings can back each other up, a connected header may serve the same purpose, but the risk assessment must cover the interlock.

What regeneration source does a desiccant rotor need?

Steam or electricity at about 120 °C. Condenser heat at 40–45 °C is too low, and chilled-water return will disturb hydraulic balance.

Why stainless steel for cleanroom chilled water?

To prevent corrosion and allow cleaning. Carbon steel can release rust into terminal coils within three years, and cleaning may require opening ceilings, which costs more than the pipe upgrade.

Which acceptance item fails most often?

Pressure difference. After air balancing, door gaps, pass-through boxes and process exhaust can drift the pressure. Test the full door-open and door-closed envelope before sign-off.

Why three smaller chillers?

Part-load efficiency, redundancy and staging. Three units follow the cleanroom load and keep one standby. Two large units would cycle and lose humidity control.

How do I verify the result?

Measure capacity, power, room temperature and humidity over a week. Compare with the design and the baseline. A cleanroom needs trend data, not a spot reading.

Further technical reading

For the design method, see Pharmaceutical Cleanroom Chiller Design. For acceptance, see Chiller Acceptance: Standards, Tests and Files. For capacity margins, see Chiller Selection Margins. For piping, see Chilled Water Piping and Insulation.

Related reading

Chiller plant group control · Water chiller sizing · Chiller plant sensors