“How long does a chiller take to install?” The honest answer is a range, not a date. For a standard 400 kW water-cooled screw chiller in a normal mechanical room, about 90 days is a realistic planning figure. The production period is largely fixed; the variable part is site readiness, installation and acceptance.
This article breaks the schedule into eight stages, identifies the four hold points that should be written into the contract, and lists the site conditions that most often delay a project.
The 90-day critical path
The stages below assume a standard machine, a conventional mechanical room and no unusual lifting. Custom units, old-building retrofits and high-level lifts add time to several stages.
| Stage | Duration | Responsibility | Critical path |
|---|---|---|---|
| Contract and technical confirmation | 7–10 days | Both parties | Yes |
| Manufacturing | 45–60 days | Supplier | Yes |
| Transport to site | 3–7 days | Supplier | Yes |
| mechanical room readiness | Parallel with manufacturing | Client | No, but often late |
| Lifting and positioning | 2–3 days | Supplier | Yes |
| Water and electrical installation | 10–17 days | Installer | Yes |
| Single-machine and system commissioning | 5–8 days | Supplier | Yes |
| 72-hour run and acceptance | 5–6 days | Both parties | Yes |
The critical path sums to 77–111 days, with a typical project around 90 days. Manufacturing is the hard constraint. A standard machine needs component procurement, assembly, pressure testing, leak testing and a factory run. Compressing 45–60 days to 30 days usually requires a premium of 5–10% and increases the risk that vacuum or pressure-hold time is shortened.
Installation and commissioning are the compressible part. Water and electrical work can be reduced from 10–17 days to about 8 days with two shifts and a ready mechanical room, but the cost is concurrent work and a higher rework risk. The real opportunity is parallel work: mechanical room preparation should run while the machine is being built. Many projects lose this window and then store the chiller in the yard while the floor is still being waterproofed.
Site readiness runs in parallel
The client-side checklist has ten items. They do not sit on the critical path, but they cause most of the delay.
| Item | Requirement | Common failure |
|---|---|---|
| Foundation | Concrete strength, anchor bolts or pockets | Base dimensions wrong; machine does not fit |
| Floor load | Checked at operating weight, including water and piping | Only empty weight checked |
| Lifting route | Door opening at least 200 mm larger than the packaged unit | Opening 100 mm narrow; wall demolished |
| Lifting point | Rated for 1.5 times the unit weight | No roof point; temporary frame needed |
| Power | Distribution board and cable installed | Transformer not upgraded |
| Water | Condenser make-up available and water quality checked | Make-up pipe undersized |
| Drainage | Floor drain and sump for accidental water | No drain; water damages the room |
| Ventilation | Mechanical ventilation or cooling below 40 °C | Sealed room exceeds 45 °C |
| Lighting | At least 200 lx | Temporary lighting only |
| Fire | Extinguishers and emergency ventilation | Added just before acceptance |
The lifting route is the most expensive omission. A packaged 400 kW screw may be 1.8–2.2 m wide; the door should be at least 2.4 m. In an old building, a 2.0 m opening may force a wall demolition or removal of the unit casing, costing several thousand pounds and a week.
Floor load must use the operating weight. A 400 kW water-cooled screw may weigh about 3.5 t empty, hold 0.3 m³ of water and weigh about 3.8 t in service. On a suspended floor, check 4 t plus piping and supports, then convert to load per square meter. Checking only the empty weight is a common mistake.
Four hold points
Acceptance should be staged. Each hold point must pass before the next begins.
1. Open-box inspection, on delivery. Check for impact damage, compare the nameplate with the contract, and count the accessories and documents. Photograph any damaged packaging. The nameplate must show the model, cooling capacity, refrigerant and voltage matching the order. The nitrogen holding pressure must be positive; a gauge at zero means a transport leak, and the unit should not be signed off until it is leak-tested.
2. Installation acceptance, after piping and electrical work. Pressure-test the water circuit at 1.5 times the working pressure and not less than 0.6 MPa; hold for 10 minutes with a drop no greater than 0.02 MPa. Test the electrical insulation, at least 0.5 MΩ for low-voltage circuits. Confirm insulation, supports and valve orientation.
3. Single-machine run. Start each machine and record starting current, running current, suction and discharge pressures, entering and leaving water temperatures, noise and vibration. Run each unit for at least two hours. The running current should not exceed 110% of the nameplate rating; the evaporating temperature approach should be 2–4 K; the condensing approach 3–5 K.
4. 72-hour system run. This is the most compressed step and the one that should not be shortened. The 72 hours should cover a high load, a low load and at least one start-stop cycle. A 24-hour test sees only one condition and cannot reveal a part-load problem. If a machine stops for its own fault for more than two events or more than four hours in total, restart the clock. External stops such as a utility outage do not count.
| Hold point | Timing | Pass criterion | If it fails |
|---|---|---|---|
| Open-box inspection | Delivery day | No damage, nameplate matches, positive holding pressure | Reject or leak-test before signing |
| Installation acceptance | After piping and electrical work | Pressure test and insulation test pass | Rectify and re-test |
| Single-machine run | After installation acceptance | Current, pressures and temperatures within range | Adjust or replace components |
| 72-hour system run | After single-machine pass | Continuous operation without a machine fault | Restart the clock |
Eight documents
Acceptance is not complete until the file is complete: nameplate photo and certificate; factory test report; electrical schematic and wiring diagram; pressure-test record; insulation-resistance record; commissioning record; 72-hour run record; operation and maintenance manual with training record.
The commissioning record is the most valuable and most often missing. It captures the machine’s new-condition pressures and temperatures, which become the baseline for judging deterioration. Without it, no one can say two years later whether a 38 °C condensing temperature is normal or high. The training record matters too: a signed attendance list and a content list settle later disputes about whether training happened.
Three delays that cost weeks
The power is not ready. The machine is installed but cannot be energized. The usual cause is a transformer upgrade that was not started early; the utility process can take 20 working days or more. Start it when the contract is signed, not when the machine arrives.
The cooling-tower position is unresolved. A water-cooled chiller needs a tower on the roof or at grade, with structural, noise, drift and property approvals. Roof space is often rejected because of waterproofing or parapet height, which forces a redesign and a new order.
The acceptance criteria are not in the contract. If the contract says only “acceptance to be agreed”, the parties will disagree about test points and duration. Attach the four hold points and the 72-hour rule to the contract, including who measures and what happens on a retest.
Payment against acceptance
A common structure is 30% on contract and technical confirmation, 60% before shipment after the factory test and client inspection, and 10% on acceptance after the 72-hour run and complete documents. This gives the supplier an incentive to finish commissioning. If the client retains 5% for warranty, state that it is payable 12 months after acceptance, and include the financing cost in the price comparison.
Payment terms change prices. A supplier asked for 90 days’ credit after delivery may add 2–4% for capital cost. When comparing bids, convert the terms to a common basis; otherwise the lowest price may not be the lowest cost.
What each acceptance document proves
The acceptance file is not a folder of paper. Each document answers a different question, and a missing one leaves a specific gap in the handover. The table turns the eight-item list into a check sheet.
| Document | What it proves | Check at handover |
|---|---|---|
| Nameplate photo and certificate | Model and serial match the order | Photo readable; serial recorded in the log |
| Factory test report | Capacity, efficiency and noise at rated conditions | Test date, laboratory, model and conditions |
| Electrical schematic and wiring diagram | As-built electrical configuration | Revisions marked; terminal numbers match |
| Pressure-test record | Piping is leak-free | Test pressure, duration and witness signature |
| Insulation-resistance record | Electrical safety | Values by circuit; date and instrument |
| Commissioning record | New-condition baseline | All design modes recorded, not only full load |
| 72-hour run record | Stable operation under load | Hourly data; no gaps; alarm log attached |
| O&M manual and training record | Operator can run and maintain the plant | Signed attendance list; site-specific set points |
The commissioning record is the most valuable and the most often missing. It is the baseline for every later “is this normal?” question. A 38 °C condensing temperature may be normal on day one and high in year three; without the day-one value, no one can tell. Ask for the record in the same format as the trend log, not a handwritten summary.
The training record is not administrative. A signed attendance sheet plus a course-content list settles the later dispute about whether the operator was shown the changeover, the alarm reset and the water treatment.
Payment can be tied to the file. A 10% retention released when the eight documents are complete is a stronger incentive than a verbal promise. Longcom’s water chiller page gives the installation and documentation scope behind this checklist.
Common questions
How long from order to operation?
About 90 days for a standard machine: 45–60 days manufacturing, 20–30 days installation and commissioning, and 5–6 days of run and acceptance. A custom unit adds 15–30 days; an old-building retrofit adds another 10–20 days.
Can the schedule be compressed to 60 days?
It can, at a cost. A production slot premium of 5–10%, two-shift installation and compressed pressure-hold time increase leak risk. If the start date is not fixed, 90 days is a better plan.
Can the 72-hour run be reduced to 24 hours?
Not without losing information. The 72 hours cover high load, low load and a start-stop cycle. If time is tight, 48 hours with a complete cycle is the minimum, and the reduction should be recorded.
What should be checked on delivery?
Three things: the nameplate matches the contract, there is no visible damage, and the nitrogen holding pressure is positive. A zero gauge means a transport leak; leak-test before signing.
What must the client prepare?
Ten items: foundation, floor load, lifting route, lifting point, power, water, drainage, ventilation, lighting and fire protection. The lifting route and the power supply cause the most delays. Allow at least 200 mm extra door width.
Can missing documents be supplied later?
The factory test report and the commissioning record should not be deferred. They prove the factory condition and set the deterioration baseline. Other documents can be supplied later, but these two cannot be recreated after the machine has run.
What are hold points?
Foundation, piping pressure test, electrical connection and performance test. Each needs a signed check before the next stage. Skipping one moves the risk downstream.
How long does it take?
About 90 days for a 400 kW chiller, with production fixed. Site readiness and the four hold points set the rest.
Further technical reading