Clean-Heating Policy: The Evidence a Project Needs

A clean-heating policy can look like a market signal and still fail to produce a bankable project. The document may offer a favorable tariff, a capital grant and an efficiency requirement, but the project only works if the tariff is available at the right hours, the grant is counted in the right place and the acceptance evidence can be produced.

This article does not review policy history. It sets out the three instruments a heat-pump hot-water project must convert into numbers, and the documents a reviewer will expect.

Three instruments, three different effects

Tariff. Time-of-use pricing changes the value of storage. A valley rate of CNY 0.25–0.35/kWh against a peak of CNY 0.90–1.10/kWh gives a spread of more than three to one. A heat pump can use that spread only if it can shift its electricity consumption, which means a tank or a larger machine running at night.

Subsidy. A capital grant reduces the investment; an operating subsidy reduces the annual bill. They are not interchangeable. Mixing them into one “subsidy” line can make a project look better than it is, because the capital grant does not recur and the operating subsidy may expire.

Verification. The acceptance rule may require metered efficiency, data upload or a third-party test. This is the instrument most often missed. A project that cannot produce the evidence may lose the payment even if the equipment performs.

A 10 m³/d example

Take 10 m³/d of hot water at 55 °C, a 40 K rise, a daily useful heat of 465 kWh and a system COP of 3.0. The daily electricity is 155 kWh.

Operating pattern Tariff Daily cost Annual cost, 350 d Configuration
All-day supply, flat rate CNY 0.65/kWh CNY 100.8 CNY 35,280 No storage
All valley charging CNY 0.30/kWh CNY 46.5 CNY 16,275 10 m³ insulated tank
All peak running CNY 1.00/kWh CNY 155.0 CNY 54,250 No storage, poor control

The difference between valley charging and peak running is CNY 38,000 a year. A 10 m³ stainless insulated tank and a control upgrade may cost CNY 15,000–20,000, so the storage is paid back in under half a year at this tariff spread.

Storage changes the machine size

If the whole daily heat must be produced in an 8-hour valley window, the input is 155 ÷ 8 = 19.4 kW. If the unit can run for 10 hours during the day, it needs 15.5 kW. The storage option therefore increases the machine capacity by about 25%. That extra capital must be counted against the saving.

Do not store at 70 °C to make the tank smaller. A higher temperature increases standing loss by about 15% per 10 K and raises the temperature class of the tank, pipe and valves. The efficient approach is a larger volume at 55 °C, with a well-insulated tank and a low inlet velocity.

Subsidy arithmetic

For a 10 t/d project with CNY 180,000 equipment cost, the valley-charging running cost is CNY 16,300 a year. A gas boiler at CNY 182.7/d for 350 days costs CNY 63,900, so the heat pump saves CNY 47,600 a year and the simple payback is 3.8 years.

Case Capital Annual running Simple payback
No subsidy CNY 180,000 CNY 16,300 3.8 years
30% capital grant CNY 126,000 CNY 16,300 2.6 years
Operating subsidy CNY 0.10/kWh CNY 180,000 CNY 10,900 3.4 years
Both CNY 126,000 CNY 10,900 2.4 years

The operating subsidy is 54,200 kWh × CNY 0.10 = CNY 5,420 a year, which reduces the running cost from CNY 16,300 to CNY 10,900. The saving against gas rises from CNY 47,600 to CNY 53,000.

Baseline matters more than the grant

If the displaced source is a small coal boiler with a fuel cost of CNY 73.4/d, the annual cost is CNY 25,700. The heat pump at CNY 16,300 saves only CNY 9,400 a year, and the CNY 180,000 investment takes about 19 years to recover. A capital grant may shorten that, but the economics are still weak. A gas boiler baseline gives a much stronger case. The policy document does not change the baseline; the project must state it.

The evidence file

Check the current efficiency standard before tender. GB 19577-2024 replaced the 2015 edition and took effect in February 2025; a bid that submits an old report can fail the qualification stage. The technical agreement should require capacity, input power and COP at −12 °C and −20 °C, with the page reference of the test report.

For acceptance, prepare the meter scheme before installation: a dedicated electricity meter, water meter, temperature sensors and a data logger. Record the commissioning baseline for at least seven days. If the policy requires a third-party review, keep the raw data, the calibration certificates and the calculation sheet. A screenshot from a dashboard is not a verification file. A grant application that cannot show the baseline and the meter boundary is incomplete.

Common questions

Does a clean-heating policy guarantee a market?

No. It provides tariffs, grants and verification rules. A project still needs a real heat load, a favorable baseline and the ability to shift or store electricity. Without those, the policy does not make the numbers work.

Is a capital grant better than an operating subsidy?

They do different things. A capital grant lowers the investment and the payback; an operating subsidy lowers the annual bill but may expire. Count each in its own line and show the payback with and without it.

How much storage is needed to use valley electricity?

Either 60–80% of daily demand in a tank or a machine 25% larger that completes the daily heat in the 8-hour valley window. The tank is usually cheaper than the extra machine capacity.

Why is 70 °C storage a poor choice?

Standing loss rises about 15% per 10 K, and the tank, pipe and valves need a higher temperature class. A larger tank at 55 °C is more efficient and easier to insulate.

Which standard should a bid report?

GB 19577-2024, effective February 2025. Confirm the report is current, covers the model and includes the test conditions. An old edition can fail the qualification review.

What if the displaced boiler is coal?

The case may be weak. A small coal boiler can have a very low fuel cost, so the heat pump saving may be only CNY 9,400 a year against a CNY 180,000 investment. State the baseline honestly and do not rely on the grant alone.

What evidence does a subsidy require?

Metered energy, installed capacity, commissioning record, invoice and a baseline. The exact list depends on the program. Ask before the design, not after the install.

How do I prove the baseline?

Use 12 months of bills or a calibrated meter. State the boundary and the weather correction. A baseline built after the retrofit cannot prove the saving.

Further technical reading

For carbon accounting, see Heat-Pump Hot Water Carbon Accounting. For payback method, see Heat Pump Payback: Separate Capex from Running Cost. For the policy case, see County Coal-to-Electric Heat-Pump Case. For storage, see Hot-Water Storage Tank Sizing.