Two quotations for a “30 kW” air-source heat pump, one at CNY 68,000 and one at CNY 96,000, are often explained as brand premium. Usually they are not. The difference sits in the coil area, the compressor type, the tank plate thickness, the installation scope and the control package. None of these is visible in the headline capacity.
A quotable comparison therefore needs two disciplines: separate equipment from installation, and normalize every line to the same condition. A price per kW without a boundary is as misleading as a capacity without an ambient.
1. Six lines that should be separate
| Line | Typical share | Pricing basis | What to verify |
|---|---|---|---|
| Heat pump | 50–60% | Per unit or per kW heating | Nominal or low-ambient capacity; compressor type |
| Storage tank | 18–25% | Per unit or per m³ | Plate thickness, 304 or 316L, insulation |
| Piping and valves | 8–12% | Per meter or lump sum | Pipe material, insulation, supports, strainers |
| Electrical and controls | 6–10% | Lump sum | Cable size, breaker, control brand, remote monitoring |
| Transport and lifting | 2–4% | Lump sum | Crane, roof access, removal of old equipment |
| Commissioning and warranty | 3–5% | Lump sum | Test scope, warranty length, response time |
The shares are experience ranges. A small project has a higher piping and installation share; a large tank raises the tank share. A quote that gives only a total leaves every missing item to be added later, and the lowest total often becomes the highest final cost.
2. The equipment price per kW
| Class | Heating capacity | Typical price | Notes |
|---|---|---|---|
| Residential monobloc | 3–7 kW | CNY 2,500–4,000 per kW | Small tank included; simple installation |
| Commercial split | 10–30 kW | CNY 1,200–1,700 per kW | Main project range |
| Large commercial | 40–80 kW | CNY 1,000–1,400 per kW | Dual compressor or dual circuit |
| Modular | Above 100 kW | CNY 900–1,200 per kW | Parallel modules and group control |
The price per kW falls with size because the compressor, heat exchanger and cabinet cost does not scale linearly. It rises with configuration: low-ambient vapor injection, high-temperature outlet, stainless cabinet, remote monitoring and explosion protection all add cost without adding nominal kW.
3. Five hidden differences
Coil area. Going from two rows to three rows adds about 8% to the coil cost but can raise winter capacity by 10–15%. A quote that says “high-efficiency fin” without rows, area or tube diameter is hiding the variable that matters most in cold weather.
Compressor type. A rotary compressor is cheaper; a scroll is 15–25% more; a two-stage or vapor-injection unit adds another 20–30%. In a cold climate, the vapor-injection premium buys capacity at −7 °C and −15 °C, not just a label.
Tank material and thickness. 304 stainless at 1.5 mm versus 2.0 mm is about 30% more material cost; 316L is over 40% more than 304. At a chloride level above 200 mg/L, a 304 tank can pit within two years. The tank is often the item that turns a cheap quote into an early replacement.
Installation scope. Does the price include lifting to the roof, removal of the old unit, pipe insulation, electrical cable, a new breaker, water connection and commissioning? A quote that excludes lifting and removal can look 10–15% cheaper before the extras arrive.
Control and monitoring. A basic controller, a BAS interface, remote monitoring and a group controller are different products. A “smart” claim without a point list and a protocol is not a deliverable.
4. A 30 kW example
At CNY 1,200–1,700 per kW, the bare 30 kW unit is CNY 36,000–51,000. Add a 3 m³ tank at CNY 6,000–12,000, piping and valves at 8–12%, electrical and controls at 6–10%, lifting at 2–4%, and commissioning at 3–5%. The installed range lands near CNY 60,000–85,000 before options.
The CNY 96,000 quote may include a larger coil, a vapor-injection compressor, a 316L tank, full lifting and removal, and a monitoring gateway. The CNY 68,000 quote may include none of these. The difference is not 40% of the same scope; it is two different scopes with the same nominal capacity.
To compare, rebuild both quotes into the six lines, then convert the equipment price to CNY per kW at the same ambient. A 30 kW nominal unit that delivers 18 kW at −7 °C is not the same as one that delivers 23 kW. The second can be cheaper per delivered winter kW even at a higher sticker price.
5. Contract terms that prevent the gap
Capacity guarantee at a stated condition. Specify the ambient, inlet and outlet. “30 kW” alone is not a guarantee.
Scope matrix. List what is included and what is by others: foundation, lifting, electrical supply to the isolator, water connection, drain, removal of old equipment, commissioning and training.
Payment against milestones. Delivery, installation, commissioning and performance test. A large advance with no performance hold weakens the owner’s position.
Variation procedure. Unit rates for additional piping, cable and lifting, agreed before work starts. Otherwise the “missing” items are priced at the contractor’s convenience.
Spare and warranty terms. Response time, excluded parts, spare supply period and extended warranty. These are part of the price, even if they are not in the equipment line.
6. A one-page comparison
| Item | Quote A | Quote B | Normalized basis |
|---|---|---|---|
| Nominal capacity | 30 kW | 30 kW | At 20 °C ambient |
| Capacity at −7 °C | 18 kW | 23 kW | Same outlet 55 °C |
| Compressor | Rotary | Scroll, vapor injection | Model and datasheet |
| Coil rows | 2 | 3 | Area and tube diameter |
| Tank | 304, 1.5 mm | 316L, 2.0 mm | Water chloride analysis |
| Installation | Excludes lifting | Includes lifting and removal | Scope matrix |
| Price per winter kW | CNY 3,778 | CNY 4,174 | Total ÷ capacity at −7 °C |
The last line is the useful one. It converts two different offers into a common basis. The cheaper sticker can be the more expensive winter machine.
Common questions
Why do two 30 kW quotes differ by 40%?
Usually coil area, compressor type, tank grade, installation scope and controls. Brand premium exists, but it is rarely the whole difference. Rebuild both into the six lines before concluding.
Is a higher price per kW always better?
No. A high price can reflect a larger coil and a better tank, or simply a weak quote. Compare winter capacity, material grade, scope and service terms, not price alone.
Should the tank be priced separately?
Yes. Tank volume, plate thickness and material are independent decisions. A bundled “free tank” is usually a small tank with a thin plate, and it may not match the draw profile.
How much does installation usually add?
For a commercial project, the balance of plant and installation often add 30–50% to the equipment price, depending on piping length, roof access and electrical work.
What is the most common hidden cost?
Lifting and roof access, removal of the old unit, electrical upgrades and additional piping. These are often excluded from the headline price and appear as variations after the order.
How should a performance guarantee be written?
State the ambient, inlet, outlet, water flow, voltage and the test method. A capacity without conditions is not enforceable, and a test without a method is not repeatable.
What should a like-for-like quote itemize?
Different coil area, compressor type, tank grade, controls, installation and warranty. One may exclude electrical work or commissioning. Compare the scope line by line, not the headline price.
What hidden scope should I check?
Cable, isolator, foundation, drain, water treatment, remote monitoring and spare parts. A low quote can leave the owner to pay for these later. Ask for a scope matrix.
Further technical reading
- Heat-Pump Product Series and Model Codes
- Heat-Pump Selection Mistakes
- Heat-Pump Spare Parts
- Heat Pump vs Gas Boiler Cost
LONGCOM can rebuild several quotes into the same six-line scope and compare them per delivered kW at the site’s winter condition. For a quote review, contact 400-878-0280 or 13002001280.