Industrial Park Hot-Water Retrofit: Define the Boundary

An industrial-park hot-water retrofit usually starts with a heat-pump quote and ends with an argument about the saving. The argument is rarely about the compressor. It is about the boundary: whether the tanks and pumps were replaced, whether the coal and electricity were measured on the same basis, and whether the baseline was a meter reading or an estimate.

The case below is a 1,800-worker park in southern China, with dormitory showers and a canteen. The existing system is a 0.5 t/h coal boiler plus three 60 kW electric storage heaters. The method is the point: measure, define the boundary, check the pipes, check the power, stage the work, and agree the accounting before comparing.

1. Measure three things before quoting

Water. Dormitory demand at 50 L per person per day plus canteen washing at 10 L gives 60 L per person, or 108 m³/day for 1,800 people. Verify with a week of water-meter readings; a park with shifts has a morning and an evening peak, not the single evening peak of a student dormitory.

Heat. At 15 °C make-up and 55 °C supply, the daily heat is 108,000 × 4.187 × 40 ÷ 3,600 ≈ 5,024 kWh. In winter, make-up at 10 °C and a 45 K rise gives 5,653 kWh, 12% more. In southern China the winter is short, but that 12% decides whether the plant needs three or four units. This project uses four 110 kW units so that three can still cover 5,653 kWh when one is serviced.

Electricity. The electric heaters, boiler auxiliaries and circulation pumps share one meter. Clamp the electric-heater circuit for three days to get the 2,114 kWh/day baseline. Coal is from the weighbridge or a stock survey, with an uncertainty often above 10%; record the source.

The baseline then reconciles: 800 kg coal/day with a total low heating value of 4,640 kWh/day and a boiler efficiency of 0.65 gives 3,016 kWh of useful heat, about 60% of the total. The remaining 2,008 kWh at an electric efficiency of 0.95 draws 2,114 kWh. The three numbers reconcile, so the savings percentage has a denominator.

2. The boundary is a commercial decision, not a technical one

Boundary Scope Best fit Risk
Heat source only Remove boiler and heaters; keep tank, pumps, pipes and terminals Tank under 5 years, insulation sound, no leaks Original tank is small and has no stratification; evening temperature still sags
Heat source + tank + pumps New units, tank, circulation pumps and controls; keep pipes and terminals Most parks Higher capex, but the peak and the pumping power are fixed
Full system Also risers and terminal mixing valves Risers over 10 years, failed pressure test, terminals below 45 °C Water shutdown and staged works; only viable during a dormitory refurbishment

Three tests decide whether the tank should be replaced: age over five years, scale over 2 mm, or cleaning cost above 40% of a new tank. One hit is enough. A new tank is about 15–20% of the project cost, but it prevents the post-retrofit evening sag and gives the new units a proper buffer volume.

3. Can the existing pipes be reused?

Galvanized steel is the common case. After eight years, the internal scale is often 1–2 mm, reducing the flow area by 15–25% and the flow by about 20% at the same head. Do not judge by the outside. Measure three points: terminal pressure, pump differential and flow in each building. A differential 30% above design with a flow 20% below design means the scale is affecting distribution; clean chemically or replace the main. After cleaning, a 0.6 MPa pressure test for 30 minutes with no drop is the acceptance.

Steam pipe cannot simply be converted to hot water. A 0.4 MPa steam line laid at a 0.003 slope with steam traps will air-bind when filled with water; the terminals alternate hot and cold, and the mineral-wool insulation is often wet and compacted. Retire the steam line or keep it for the canteen steamer, and lay a new hot-water main.

Redo the insulation for the hot-water duty: 30 mm elastomeric insulation, glass-cloth wrap and two coats of paint; prefabricated insulated pipe for buried runs. The existing insulation can be retained only if a cut shows a dry, non-powdered inner layer and the surface is within 5 K of ambient.

4. The electrical account usually improves

The intuitive fear is that more equipment means a bigger supply. The arithmetic is the other way: 1 kW of electric resistance gives 1 kW of heat; a heat pump gives about 3 kW. This park had 180 kW of electric heaters. After the retrofit, the heat pump draw is about 152 kW plus 30 kW of pumps, lower than the pre-retrofit 180 kW plus 30 kW of boiler auxiliaries.

Check the transformer: 630 kVA, pre-retrofit 180 kW heaters + 30 kW boiler + 150 kW general load = 360 kW, or 400 kVA at 0.9 power factor, 63% loaded. Post-retrofit 152 + 30 + 150 = 332 kW, or 369 kVA, 59% loaded. No upgrade is needed, and the capacity freed from the heaters is available for phase two.

Three checks cannot be skipped: keep the transformer below 80% loading; check the starting current, because a fixed-speed unit can draw 5–7 times rated and five starting together can pull the bus down by more than 5%, while a VSD unit starts at 1.2–1.5 times; and check the cable ampacity, because a 35 mm² copper cable rated 90 A is adequate for one 68 A unit, but aluminum or conduit derating may not be.

5. Retrofitting without stopping production

The park works 08:30–17:30, and the shower peak follows. Any water shutdown must be restored before 17:00. Stage the work in three batches of two buildings, four days each, plus five days of commissioning: 17 days with no whole-park shutdown.

Keep one 60 kW electric storage heater beside the canteen as a temporary source for the duty dormitory and canteen, about 8–10 m³/day for 150 people. The temporary source does not need to cover the whole park; it needs to cover the people who cannot be without water. Agree that list with the production manager before work starts.

Limit each building to an eight-hour shutdown: isolate and cut in the morning, pressure-test, flush and restore in the afternoon, with water back by 17:00. Post notices three days ahead with the times and the temporary water points. In practice, poor notification causes more complaints than the work itself.

Lifting and hot work are separate permits. A 16 t crane stands inside the dormitory compound, clear of the fire lane and the goods route; lifting is scheduled during the lunch break with the area cleared. Welding is in a designated outdoor area, with a fire permit, at least 30 m from the workshop and a spark tray. These procedural steps are the real boundary of “no production stop”.

6. Agree the accounting before comparing

Electricity-meter method. Pre-retrofit 2,114 kWh/day, post-retrofit 1,570 kWh/day, 330 days: 698,000 kWh to 518,000 kWh, a 26% reduction. This counts only electricity, not coal, so it understates the effect. If the pre-retrofit system were all electric, the same method could show more than 60%, and an untrained reader would conclude the second project is better.

Heat-meter method. Fair, but only if both periods have a meter. This park had no pre-retrofit heat meter; the baseline was estimated from water volume and temperature difference at 5,024 kWh/day. The post-retrofit meter read 4,900–5,100 kWh/day, within 3%. The estimate must be labeled as an estimate, or acceptance will compare a measurement with a guess.

Coal-equivalent method. For external reporting, 0.1229 kgce/kWh and 0.714 kgce/kg coal give 831 kgce/day before and 193 kgce/day after; at 330 days, 274 tce to 64 tce, a 77% reduction. Using the equivalent-value factor of 0.30 kgce/kWh gives 1,206 to 471 kgce/day, a 61% reduction. The same project and the same year differ by 16 percentage points; the report must state the factor.

Basis Before After Change
Electricity meter 698,000 kWh/y 518,000 kWh/y −26%
Coal equivalent, 0.1229 274 tce/y 64 tce/y −77%
Coal equivalent, 0.30 398 tce/y 155 tce/y −61%

7. The payback is a set of conditions

Capex at 620 CNY per person for 1,800 people is 1.116 million CNY, including units, tank, pumps, controls, roof foundation and part of the main replacement. The unit price varies by ±25% with tank material, lifting difficulty and pipe replacement.

Annual saving: 180,000 kWh × 0.7 CNY ≈ 126,000 CNY, plus 264 t coal × 900 CNY ≈ 238,000 CNY, total 364,000 CNY. Static payback 1.116 million ÷ 364,000 ≈ 3.1 years. Three conditions must hold: electricity at 0.7 CNY/kWh, coal at 900 CNY/t, and 330 days at a load factor above 0.7. At 0.85 CNY/kWh the payback shortens to 2.8 years; at 1,200 residents it lengthens beyond 4.5 years.

Two benefits are usually left out: no boiler operator or pressure-vessel inspection after the coal boiler is removed, saving several thousand CNY a year; and no dust or sulfur dioxide, reducing boundary complaints. These are real but hard to monetize; describe them qualitatively.

Retrofit decision matrix: what to replace and what to keep

The survey produces a scope decision, not a wish list. The matrix below converts six common site findings into a boundary: heat source only, heat source plus tank or mains, or a full terminal upgrade.

Existing condition Recommended boundary Field evidence
Tank under 5 years, insulation sound, no leak Heat source only Wall thickness at least 90% of design; welds dry
Tank scale 2 mm or more, or a leak Heat source plus tank Cleaning quote above 40% of a new tank
Galvanized riser over 8 years, flow down over 20% Heat source plus main Pressure drop up 30% at 20% lower flow
Terminal mixing valve old, outlet below 45 °C Include terminal work Measured outlet at the worst point
Transformer loading above 80% Stagger starts or upgrade Apparent power divided by rated capacity
Existing steam boiler has a pressure-vessel registration Deregister or convert first Registration closed before removal

Two findings that point to the same extended boundary are the signal to widen the scope. A tank with scale and a riser with restricted flow will not be fixed by a new heat pump alone; the unit will run at a higher condensing temperature and the complaints will move from the boiler room to the shower. A single row pointing to “heat source only” is the case for a minimal retrofit, provided the tank and water main pass their own checks.

Put the matrix in the survey report and attach the measured evidence. A scope defined by opinion cannot be priced or accepted; a scope defined by wall thickness, pressure drop and outlet temperature can. Longcom’s air-source heat pump page lists the unit configurations used in this kind of staged retrofit.

Common questions

Should we replace the tank with the heat pump?

If it is over five years old, has 2 mm of scale, or cleaning costs 40% of a new tank, yes. Otherwise the old tank can stay, but check its volume against the evening peak.

Can the existing galvanized pipe be reused?

Test it. If the pump differential is 30% above design and the flow 20% below, clean or replace. A 0.6 MPa, 30-minute pressure test is the acceptance.

Will the electrical supply need upgrading?

Usually not. A heat pump draws about one-third of the resistance power for the same heat. Check transformer loading, starting current and cable ampacity before concluding.

How long does the retrofit take?

This park took 17 days in three batches, with no whole-park shutdown. The critical path is the temporary source, the eight-hour building shutdown and the pressure test.

Which savings figure should go in the report?

State the basis. A 26% electricity reduction, a 77% coal-equivalent reduction and a 61% equivalent-value reduction are all true for the same project; they are not interchangeable.

What is the most common boundary mistake?

Replacing only the heat source while keeping an undersized, scaled tank, then blaming the heat pump for the evening temperature sag.

What boundary?

The retrofit boundary decides the baseline. Include the existing plant, the new heat pumps and the storage. A boundary that moves makes savings invisible.

What baseline?

Twelve months of metered heat and power. Normalize for weather and output. A design baseline is not a measurement.

Further technical reading