Sizing questions come in a predictable order: what the volume means, what the pool actually loses, how fast it must heat, how the water and electricity get there. Twenty answers below follow that order.
| Input | Unit | Typical magnitude |
|---|---|---|
| Surface evaporation, indoor | W/m² | 100–200 uncovered |
| Surface evaporation, outdoor | W/m² | 200–350 uncovered |
| Design ΔT across unit | K | 4–5 |
| First heat-up allowance | hours | 24–72 |
1. Volume, surface and the three water accounts
Q1. How is the effective water volume calculated?
Geometric volume minus the displacement of fittings, steps and equipment, plus the water in the balance tank and pipework if it is in circuit. For a pool with an overflow gutter, the balance tank volume matters because it is heated too.
Q2. Why is kilowatt-per-cubic-meter estimating unreliable?
It assumes every pool of a given volume loses heat at the same rate. In reality a 500 m³ pool with a 400 m² surface in a windy exposed position can lose twice what a 500 m³ pool with 200 m² in a sheltered indoor hall loses.
Q3. What evaporation rate should be used at design stage?
Start from the surface heat-loss figure — roughly 100–200 W/m² indoors, 200–350 W/m² outdoors for uncovered water — then correct for water temperature, air velocity and humidity. A night cover changes the annual figure far more than the design figure.
Q4. How does make-up water become a load?
Every cubic meter of cold make-up water must be raised to pool temperature: 1 m³ and 10 K is about 11.6 kWh. A pool losing 3% of its volume daily at 10 K therefore carries a continuous load of roughly 1.5 kW per 100 m³, before the evaporation it causes.
Q5. Do convection and radiation need separate numbers?
They are usually estimated together with evaporation or taken as a fraction of it. For outdoor pools wind dominates and should be handled explicitly; for indoor halls the envelope and air distribution control them.
2. First heat-up and unit count
Q5. How is first heat-up power calculated?
Net heat equals mass × 4.186 kJ/kg·K × temperature rise, divided by the hours allowed; then add the holding loss simultaneously, because the pool is losing heat while it warms. A 500 m³ pool, 12 K, 48 hours: about 145 kW net, roughly 170 kW installed with margin.
Q6. How many units should that become?
Enough to cover the holding load with one module out of service, and to give a usable part-load step. In practice: ≤30 kW one unit; 30–80 kW two; 80–160 kW two or three; above 160 kW modular.
Q7. How is circulation flow fixed?
Two constraints: the unit’s design temperature difference (usually 4–5 K) and the pool’s turnover period. The higher flow governs, and the unit’s minimum flow is a hard floor — below it the exchanger fouls and protection trips.
Q8. How is pump head determined?
Sum the pressure drops of strainer, exchanger, valves, fittings and pipe at design flow, then add the static and residual requirements and a margin. On retrofits, measure the existing pump’s actual duty rather than trusting its nameplate.
Q9. What if the client’s heat-up time is unrealistic?
Show the arithmetic and offer alternatives: a larger unit, a buffer tank, or a temporary heater for the initial fill. Promising a 12-hour heat-up for a 1000 m³ pool and delivering 36 hours is a commissioning dispute waiting to happen.
3. Electrical, plant room and documentation
Q9. How much electrical capacity is needed?
Rated input of all modules plus pumps, controls and any auxiliary heat, with starting current allowance for fixed-speed compressors. Check the available supply at the board, not at the meter, and confirm cable and protection ratings.
Q10. How much plant room area should be allowed?
Roughly the unit footprint plus intake clearance on the stated sides, service access for coil cleaning, and space for the bypass and strainer. Multi-module arrays need the clearance multiplied, which is where tight rooms fail.
Q11. What should a selection sheet contain?
Project conditions, capacity and COP at those conditions, the derating curve, water flow range and pressure drop, exchanger material and thickness, connection sizes, electrical data, protection functions, unit count and control arrangement.
Q12. Which items are most often missing from a proposal?
Make-up water load, the derating curve, the pressure drop at rated flow, and the electrical starting current. Each of them surfaces later as a commercial argument.
Q13. Who should produce the selection, supplier or design institute?
The supplier produces the equipment selection with conditions attached; the design institute owns the system and the hydraulics. The failure mode is a supplier selection issued without conditions being adopted as the design.
4. Scenario differences and budget
Q13. How much does indoor versus outdoor change the sizing?
Indoors, evaporation is lower and the hall is controlled, but dehumidification becomes part of the duty. Outdoors, wind and solar gain dominate and the installed capacity is typically 20–40% higher for the same water volume.
Q14. How are spa and hot spring pools sized?
From capacity data taken at 38–42 °C water, not at 27 °C. Pressure ratio is higher, COP lower, and a buffer tank is normally required so that bather surges do not cycle the compressor.
Q15. Inverter or fixed speed, from a sizing point of view?
If the holding load is under about half the nominal capacity, inverter. If it is close to nominal, fixed speed is fine and cheaper. The ratio, not the marketing, decides.
Q16. How is a retrofit load rechecked?
Recompute the holding load from the existing pool’s real operation — measured daily temperature drop with the heater off, actual make-up rate — rather than from the original drawings, which rarely match the pool as built.
Q17. When the budget is limited, what should be protected first?
Flow and filtration, the exchanger material, and the intake clearance. Cutting the bypass, the strainer or the material grade saves a small percentage and converts a working installation into a service case.