A chiller replacement is not a catalog transaction. The new machine must pass through a door, sit on a base that was designed for the old machine, connect to pipes that were cut and welded in place, and start without straining the shell. Most replacement problems occur before the first start: the lift, the base and the pipe strain.
This article covers the physical installation of a replacement chiller. The example is a 400 kW water-cooled screw machine weighing 3.5 t in an existing basement mechanical room.
Survey before the crane
Measure the access route, not the doorway. A 3.5 t machine may be 2.2 m wide and 3.5 m long; a 2.0 m door is a wall, not an opening. Check the corridor width, the turning radius, the floor loading and the overhead clearance. A basement mechanical room may have a removable panel or a hatch; confirm the hatch size and the crane’s lifting height.
Weigh the unit with the shipping skid, the refrigerant charge and any water in the bundle. The rigging load is the weight plus the dynamic factor; use 1.5 times the static weight for the sling and the shackle, and confirm the floor’s point load during the lift. Do not use the machine’s eyebolts for a lift they were not designed for; check the manufacturer’s lifting plan.
| Survey item | Record | Pass condition |
|---|---|---|
| Unit weight | 3.5 t shipping | Rigging rated 5.25 t |
| Route width | Clear opening | Unit width + 300 mm |
| Floor load | Point load during lift | Within slab capacity |
| Overhead | Hook height | Unit height + rigging + 500 mm |
The base is not a housekeeping pad
The old base may be a concrete plinth with anchor bolts that no longer match. Do not drill new anchors into a cracked pad without an engineer’s check. The new base should be level, isolated from the slab where vibration transmission matters, and grouted under the full footprint.
Set the machine on shims or a grout bed, level to 2 mm/m, then tighten the anchors. A machine that rocks will transmit vibration to the pipes and the slab. A machine that is bolted down on a twisted base will distort the shell and misalign the coupling.
Leave a gap for grout, use a non-shrink grout, and check the anchor torque after the grout has cured. Do not grout the base before the pipes are connected; you may need to move the machine a few millimeters to align a flange.
Pipe strain is the silent killer
Every pipe connected to the chiller must have its own support. The chiller is not a pipe hanger. A 6 m length of DN150 filled with water weighs about 1 t; if that weight is carried by the evaporator flange, the shell will deflect and the tube sheet will leak.
Support the pipe within 1 m of the flange, use a flexible coupling or a gasketed joint, and align the flange with the machine before tightening. Do not use the flange bolts to pull the pipe into alignment. Check the gap with a feeler gauge; a 2 mm angular gap over a DN150 flange is a bending moment.
| Check | Method | Reject |
|---|---|---|
| Pipe support | Independent hanger within 1 m | Weight on the flange |
| Flange gap | Feeler gauge, four points | Gap over 1 mm |
| Coupling | Alignment gauge | Angular or parallel misalignment over spec |
| Anchor | Torque wrench | Loose or over-torqued |
Flush before you connect
Cutting and welding the existing pipe leaves slag. Flush the new section through a temporary bypass before it enters the chiller. Fit a strainer on the chiller inlet and clean it after the first 24 hours. A handful of slag in a brazed-plate evaporator can block a passage and cost more than the flush.
Pressure-test the new section at 1.5 times the design pressure, then isolate the chiller and flush the loop. Do not hydro-test the chiller shell with the pipe attached unless the manufacturer allows it; the shell may have a lower test pressure than the pipe.
Electrical and controls
Check the nameplate voltage, full-load current and starting method. A new machine with a soft starter may need a different breaker setting from the old direct-on-line unit. Confirm the cable size for the actual current, not the old cable. Separate the signal cable from the power cable; a VFD on the compressor can induce noise in a 4–20 mA sensor.
Verify the rotation before the first loaded start. A screw compressor can be damaged by reverse rotation in seconds. Bump the motor with the coupling disconnected or use the manufacturer’s rotation check. Confirm the flow switch, the freeze stat and the high-pressure cut-out are wired to the correct terminals.
Hold points
Do not proceed to the next step without a signature at each hold point: route survey, base and anchors, machine set and level, pipe alignment and support, flush and pressure test, electrical rotation, first start. The signature is not bureaucracy; it is the evidence that the next step was not built on a hidden defect.
Boundary
A like-for-like replacement with the same footprint and connections is simpler than a change of model. If the new machine is heavier, wider or has a different bundle, the base, the door and the pipe may all change. Price the enabling works separately from the chiller; they are often the larger number.
Common questions
How heavy is a 400 kW chiller?
A water-cooled screw machine of that size is often 3–4 t shipping. Use the actual shipping weight and a rigging factor of 1.5; do not estimate from the capacity.
Can I reuse the old concrete base?
Only after an engineer checks its condition, level and anchor capacity. A cracked or twisted base will distort the new shell. A new grouted base is usually cheaper than a repair.
Why do the pipes need independent supports?
A water-filled DN150 pipe can weigh about 1 t over 6 m. If that weight sits on the chiller flange, the shell deflects and the tube sheet can leak.
Do I need a flexible coupling?
It reduces vibration transmission and makes alignment easier, but it does not replace a proper support. Use both: a support within 1 m and a flexible coupling at the flange.
When should I flush the new pipe?
Before it connects to the chiller. Weld slag and debris can block a plate or a tube. Flush through a temporary bypass, fit a strainer and clean it after the first day.
How do I check rotation?
Bump the motor with the coupling disconnected, or use the manufacturer’s rotation check. Reverse rotation can damage a screw compressor in seconds.
What rigging plan?
Load, center of gravity, lift path and floor capacity. A plan signed by the rigger, not a sketch on site.
What pipe strain?
Measure flange alignment before bolting. Pulling pipes into place strains the shell and voids the warranty.
Further technical reading