Small guesthouses, B&Bs and inns rarely have the space, the power or the cash for a conventional central plant. The binding constraints are usually not the price of the heat pump but the roof area, the electrical supply and the owner’s refusal to close during the season. An 18-room guesthouse with 6 m² of usable roof, a single-phase supply and 18 electric storage heaters is a useful example of what can be done within those limits.
The figures below are an illustrative retrofit, not a quotation. The same method can be re-run with the actual room count, occupancy, tariff and roof conditions.
1. Decide what to keep before pricing anything
A guesthouse usually has one of three existing systems. The right retrofit depends on how much life is left in the existing equipment, not on which heat pump is on promotion.
Distributed electric storage heaters. Typically 60–100 liters and 2 kW per room, with a tank life of six to eight years and a magnesium anode that should be replaced every two years. Remove the whole batch if two of these are true: the tank is more than six years old, the anode has never been changed, or the heating element has more than 2 mm of scale. Keep only newer units as top-floor boost or winter backup. Do not connect them in series with the new system: the series connection creates a 2–4 liter dead leg that becomes stagnant and smells in summer.
Roof solar with electric backup. This is usually the lowest-cost retrofit because the collectors and tank remain. Add a heat pump to top up the tank: solar heats first on sunny days, and the heat pump brings the tank to 55 °C at night or in rain. The conditions are a tank of at least 2 m³ and about 2 m² of roof for the outdoor unit. Connect through a plate heat exchanger or use a tank with an internal coil; an open solar tank must not be connected directly to the heat-pump water side, because dissolved oxygen will corrode the heat exchanger years earlier than expected.
Small gas boiler or calorifier. Keep the distribution and terminals, remove the boiler, cap the gas line and complete the supply cancellation. This route has the most hidden work: gas capping may need approval, the boiler room becomes a tank room, and the flue has to be removed and the roof made watertight. Allow two extra days and a higher budget than the other two routes.
| Existing system | Keep | Add | Indicative budget | Best condition |
|---|---|---|---|---|
| 18 electric storage heaters | Some terminal mixing valves and branches | Split heat pumps, tank, circulation, return | USD 6,300–7,700 | Tanks over six years old: replace the batch |
| Solar plus electric backup | Collectors, tank, risers | Heat pump, plate heat exchanger or coil tank | USD 3,500–4,900 | Tank at least 2 m³; 2 m² roof free |
| Small gas boiler | Distribution, terminals, pumps | Heat pump, tank, gas capping | USD 5,600–7,000 | Gas cancellation possible |
2. The load is small; the tank is the problem
Assume 18 rooms, two guests per room, 55% annual occupancy and 110 liters per guest per day:
18 × 2 × 0.55 × 110 ≈ 2,180 liters/day, or about 2.2 m³/day.
At a 45 K rise, the daily heat is 2,200 × 4.186 × 45 ÷ 3,600 ≈ 115 kWh. A 2 m³ tank covers roughly one day’s demand and gives useful buffering.
The immediate consequence is that a monobloc unit with an integrated 200–300 liter tank cannot serve 18 rooms. That is not a criticism of monoblocs; it is arithmetic. A 300 liter tank is a three-to-five-room solution. The guesthouse needs a split system: outdoor unit on a wall, separate 2 m³ tank on the ground floor.
Refrigerant line limits. Many split systems allow 15 m of refrigerant pipe and 5 m of height difference. Beyond that, apply the manufacturer’s correction: roughly 1–2% capacity loss per extra meter and additional refrigerant charge. Fit oil-return bends every 3 m; without them, oil returns poorly at low load in winter and the compressor wears. Keep 0.5 m clear at the air inlet and 2.5 m clear at the discharge.
Tank weight. A 2 m³ tank weighs about 2.0 t full, 2.2 t with the shell and base. On a 1.4 × 1.4 m base, that is about 11 kN/m². A guesthouse roof or terrace is often designed for 2.0 kN/m² live load, a difference of more than five times. Put the tank on the ground floor, under the stairs or on an independent external base. If it must go on a roof, span it across structural beams and obtain a structural calculation; two steel plates are not a foundation.
Access. A 2 m³ vertical tank is often 1.1 m in diameter and 1.9 m high. A 2.2 m room height is just enough, but an 0.8 m door will not pass it. Measure the door, the stair turn and the lift before ordering. A sectional tank or a horizontal tank may be the only way in; discovering this after delivery costs more than the tank.
3. Pipework without breaking walls
Reverse the existing riser into a return. This is the cheapest move in a small retrofit. The original system has a hot-water riser and branches on each floor. Add an automatic air vent at the top of the riser and a return pump at the bottom. Water is supplied from the ground-floor tank up the original riser and returns down the same riser to the tank. This avoids new risers and ceiling openings. The air vent must remain accessible, usually in the top-floor shaft.
External pipe on the façade. For old buildings without shafts, run the hot-water pipe externally with 30 mm closed-cell insulation and an aluminum jacket. Support it every 1.5 m, sleeve the wall penetrations and seal them against water. External pipe loses 10–15% more heat than concealed pipe, but it is accessible: a leak in winter is visible immediately, which suits an unstaffed guesthouse.
Pressure reduction on each floor. In a two- or three-story building, the static difference between bottom and top can be 0.15–0.25 MPa. The top shower becomes weak; the bottom hose bursts. Fit an adjustable pressure-reducing valve at each floor branch, set to 0.2–0.3 MPa. If the hot and cold pressures at a fixture differ by more than 0.05 MPa, the mixing valve will fluctuate; add a second regulator on the low-pressure side.
Single-phase capacity. An 8 kW single-phase unit draws about 36 A. Two units starting together draw nearly 72 A, while a guesthouse supply is often 40–50 A. Three options: stagger the starts by at least 30 seconds with a current interlock; change one unit to three-phase 8 kW (about 13 A); or reduce to 6 kW and enlarge the tank. An upgrade application can take weeks in a rural area, so decide at design stage, not at commissioning.
| Constraint | Limit | Practical response |
|---|---|---|
| Refrigerant pipe | 15 m typical | Keep within limit; add charge and oil-return bends |
| Height difference | 5 m typical | Ground-floor tank; wall-mounted outdoor unit |
| Tank base load | About 11 kN/m² | Ground floor or structural calculation |
| Door width | 0.8 m common | Sectional or horizontal tank |
| Single-phase supply | 40–50 A common | Stagger starts, three-phase unit, or 6 kW |
4. Noise at night
An 8 kW unit typically produces 52–58 dB(A) at 1 m. Using the point-source rule of 6 dB per doubling of distance, 3 m gives 42–48 dB(A). Through a 24 cm brick wall and double glazing, the bedroom level is often 30–35 dB(A). But if the unit is within 1.5 m of a guest-room window, the low-frequency component is still audible. Point the discharge away from the rooms, fit 10 mm anti-vibration pads, and stop the unit after 22:00 if the tank can carry the night load.
Do not rely on a brochure sound level measured in an anechoic chamber. A wall and a reflective courtyard can add 3–6 dB. Measure at the nearest window after installation; if the night level is above the local limit, move the unit or add a barrier before the season starts.
5. A three-day switchover without closing
Do the work in the quiet season, Monday to Thursday, in three batches of six rooms. Day one: set the outdoor units and tank, run the refrigerant pipe and electrical supply; rooms remain open, with some roof noise. Day two: switch the water side, shutting water only from 10:00 to 16:00, with two mobile electric heaters at the far end. The six-hour gap between checkout and check-in is usually enough. Day three: commission, flush and inspect room by room, then remove the old units.
The sequence matters. Connect the new system, pressure test at 0.8 MPa for 30 minutes, confirm no leak, then flush. Flush volume should be three times the pipe volume: for 18 rooms the combined mains and branches are about 0.2 m³, so flush about 0.6 m³, plus 2 m³ if the tank is included. Only after turbidity is acceptable should each room be switched over. Removing the old system first is the most common way to end up with a floor and no hot water.
The cost of closing for three days is easy to calculate: 18 rooms at 80% occupancy and USD 55 average rate is about USD 2,400. The extra labor and mobile-heater rental for phased work is about USD 400. Put both numbers in the proposal; otherwise “can we stay open” becomes a verbal promise between the owner and the installer.
6. Economics that can be re-run
Inputs: 2.2 m³/day, 10 °C inlet, 55 °C outlet, 300 operating days and USD 0.105/kWh (about CNY 0.75). Daily heat is 115 kWh.
The existing electric system uses about 121 kWh for heating at 95% efficiency, plus 18 kWh for standing losses across 18 tanks, total 139 kWh/day. The heat pump at a site COP of 3.0 uses about 38 kWh for heating, plus 1.2 kWh for circulation and 2 kWh for tank loss, total about 41 kWh/day.
Saving: 139 − 41 = 98 kWh/day, or about USD 10.3/day. Over 300 days, about USD 3,090/year. Capital: two 8 kW split units USD 3,650; 2 m³ stainless tank USD 770; refrigerant pipe and brackets USD 310; water-side modification and circulation USD 1,120; electrical works USD 420; installation and commissioning USD 840. Total about USD 7,100. Simple payback about 2.3 years.
Two variables dominate. At USD 0.077/kWh (CNY 0.55), the annual saving falls to about USD 2,265 and payback stretches to 3.1 years. If average occupancy falls from 55% to 40%, water and savings fall by about 27%, giving a payback of about 3.2 years. If solar is retained and supplies 30% of the heat, the saving falls to about USD 2,160, but capital falls to about USD 4,200, so payback shortens to about 1.9 years. Keeping solar is not a compromise; it is spending money only on the gap.
| Scenario | Annual saving | Capital | Simple payback |
|---|---|---|---|
| Base: USD 0.105/kWh, 55% occupancy | USD 3,090 | USD 7,100 | 2.3 years |
| Tariff USD 0.077/kWh | USD 2,265 | USD 7,100 | 3.1 years |
| Occupancy 40% | USD 2,260 | USD 7,100 | 3.2 years |
| Solar retained, 30% contribution | USD 2,160 | USD 4,200 | 1.9 years |
This excludes maintenance. Heat-pump cleaning and refrigerant checks cost USD 40–70/year; electric heaters need descaling and anode replacement at USD 11–21 per unit, or USD 200–380/year for 18 units. Including maintenance widens the heat-pump advantage by USD 130–280/year, a point often missing from quotes that compare electricity alone.
7. Boundaries and common errors
Three guesthouses should not retrofit. One with annual occupancy below 25% and a tariff below USD 0.07/kWh, where the saving does not cover the capital. One with no external wall for the outdoor unit and no 2 m² for a tank. One at an altitude where winter air stays below −15 °C: a standard-temperature unit loses more than half its capacity, and a low-temperature unit with electric backup adds more than 40% to the cost.
The common errors are predictable. Connecting the old electric tanks in series with the new system creates stagnant dead legs and unequal pressures at the mixing valve. Running a refrigerant line to 20 m without correction works in summer and loses 5 °C in winter. Putting a tank on a terrace without a structural check cracks the waterproofing within a year. Installing supply without return leaves guests waiting 40 seconds for hot water, and the complaints arrive with the first morning cohort.
A subtler error is sizing the heat pump on the water volume after guests start saving water. Behavior and metering can reduce actual use to 70–80% of the design figure, but the design must still use the allowance; otherwise the sold-out week runs short. Take the redundancy from two units, not from an optimistic water estimate.
8. Common questions
How long does an 18-room retrofit take, and must it close?
Three days in three batches of six rooms, with water off from 10:00 to 16:00 and mobile heaters covering the gap. The guesthouse stays open. A full closure would take two days but cost about USD 2,400 in lost room revenue at 80% occupancy.
Should the old solar system be removed?
No, if the tank is at least 2 m³ and the collectors are sound. Keep solar for preheat and let the heat pump top up. Connect through a plate heat exchanger or a coil tank to keep oxygen out of the heat-pump circuit.
Where can a 2 m³ tank go with only 6 m² of roof?
Not on the roof unless a structural engineer approves it. A full tank imposes about 11 kN/m², more than five times a typical roof live load. Put it on the ground floor, under the stairs or on an external base, and keep the refrigerant line within 15 m and the height difference within 5 m.
What saving can be expected?
At 2.2 m³/day and USD 0.105/kWh, the existing system uses about 139 kWh/day and the heat pump about 41 kWh/day, saving about USD 3,090/year. At USD 0.077/kWh the saving falls to about USD 2,265 and the payback extends from 2.3 to 3.1 years.
Will the outdoor unit disturb guests at night?
At 1 m the unit is typically 52–58 dB(A); at 3 m, 42–48 dB(A), and inside a brick and double-glazed room, 30–35 dB(A). If it is within 1.5 m of a window, the low-frequency tone is still audible. Point the discharge away, fit anti-vibration pads and stop the unit after 22:00.
Can two 8 kW units run on single-phase power?
Not if they start together: 36 A each, 72 A combined, against a 40–50 A supply. Stagger the starts by 30 seconds with a current interlock, change one unit to three-phase (about 13 A), or use 6 kW units with a larger tank.
Longcom Environmental Protection Equipment Co., Ltd. can review the existing system, confirm what can be retained, size split units and tanks, and prepare a phased switchover sequence. Send the room count, tariff and roof photos to admin@longk.com or call 400-878-0280.
Costs, capacities and savings are illustrative and must be recalculated with the actual guesthouse demand, local tariff, roof structure and electrical supply.
What comes first?
The hot-water peak, not the equipment. Measure the morning draw and the storage space. A guesthouse has a short, sharp peak.
What disruption?
Keep the existing boiler during changeover. A staged retrofit avoids a cold night. Plan the pipe tie-in during low season.