Chiller Changeover: Commission in One Night

A chiller changeover in an operating plant is a scheduled outage, not a construction project. The new machine is on site, the old one is isolated, and the plant needs cooling again before Monday. The commissioning must be compressed into a night window without skipping the checks that prove the machine.

This article describes a one-night changeover for a 400 kW replacement. The sequence is pre-outage, isolation, flush, start, four load stages and a 24-hour trend.

Before the night

Pre-commission everything that can be tested without the plant. Check the new chiller’s rotation, control wiring, sensor calibration and refrigerant charge. Pressure-test the new pipe section and flush it through a temporary bypass. Confirm the temporary chiller or the remaining duty machine can carry the critical load.

Write a switchover schedule with times, not tasks: 18:00 isolate, 19:00 drain, 20:00 cut and connect, 23:00 flush, 01:00 start, 02:00 load stages, 06:00 hand back. Add a 2-hour contingency. A schedule with tasks but no times always runs late.

Stage Time Hold point
Isolate and lock 18:00 Zero energy confirmed
Drain and cut 19:00 Loop isolated, water contained
Set and connect 20:00 Base level, flange gap
Flush and fill 23:00 Strainer clean, air vented
Start and stage 01:00 Rotation, pressures, approach

Isolation and drain

Close the isolation valves, lock them, and confirm the pump cannot start. Do not rely on a valve that has not been exercised for a year. Drain the loop into a clean tank, not the floor drain; the water may contain glycol or treatment chemicals.

Cut the pipe with a cold saw or a pipe cutter, not a torch, if the loop still contains refrigerant or combustible insulation. Cap the open ends and label them. Photograph the old connections before cutting; the new machine may not have the same nozzle orientation.

Set, connect, flush

Set the machine on the base, level it, and connect the pipes with independent supports. Check the flange gap at four points. Fill the loop with treated water, vent the high points and run the pump through a temporary strainer. Flush until the strainer is clean, then replace the strainer element and record the pressure drop.

Do not use the chiller’s evaporator as a flush strainer. If the loop is dirty, flush through a bypass. A new machine should not see the debris of the old pipe.

First start

Check rotation, then start the pump before the compressor. Confirm flow at the flow switch, then start the compressor at the minimum load. Record the suction and discharge pressures, the entering and leaving water temperatures and the compressor current at the first steady point.

Listen for surge or liquid carry-over. A screw machine should run smoothly; a centrifugal machine at low load may surge. If the machine alarms in the first 10 minutes, stop and diagnose; do not reset repeatedly.

Four load stages

Load the machine in four steps: 25%, 50%, 75% and 100%. Hold each step for 30 minutes, or until the water temperature is steady. At each step, record the cooling capacity, the power, the evaporator approach, the condenser approach, the chilled-water flow and the leaving-water temperature.

Load Hold Acceptance
25% 30 min Stable, no surge, approach within 2 K
50% 30 min Capacity and power within 5% of the map
75% 30 min No abnormal vibration or noise
100% 30 min Current below nameplate; safety devices not tripped

The 100% step may not be possible at night if the plant load is low. Use a temporary load bank or the process load; do not fake full load by opening a bypass. A machine that has never run at full load has not been commissioned.

Approach is the proof

The evaporator approach and the condenser approach are the best single proof of a clean, correctly charged machine. At design flow and full load, compare the measured approach with the manufacturer’s data. A 2 K deviation is a finding; a 5 K deviation is a reason to stop and investigate.

Also record the compressor current at each stage and compare it with the performance map. A current that is 10% above the map at the same condensing condition suggests a refrigerant overcharge, a fouled exchanger or a sensor error.

24-hour trend

Leave the machine running and trend for 24 hours after handover. Watch the leaving-water temperature, the approach, the current and the alarm log. A machine that passes a 30-minute stage can fail at 04:00 when the load falls and the condenser water gets cold. The trend is the evidence for the acceptance signature.

Hand over the records: the switchover schedule, the flush log, the stage table, the 24-hour trend and the alarm list. The next technician needs the baseline, not a verbal “it’s fine”.

Boundary

A one-night changeover works when the new machine is pre-tested and the pipe connections are planned. If the new machine is a different model with different nozzle positions, the pipe modification may need two nights. Do not compress a mechanical modification into a commissioning window; the cost of a failed start is higher than the cost of a second night.

Common questions

Can a chiller be commissioned in one night?

Yes, if the machine is pre-tested, the pipe is pre-fabricated and the load is available. The four load stages and a 24-hour trend still need to be completed; the night is for the switch, not for skipping proof.

What are the four load stages?

25%, 50%, 75% and 100%, each held for 30 minutes or until steady. Record capacity, power, evaporator and condenser approach, flow and leaving-water temperature at each stage.

Why is approach the best proof?

The approach reflects heat-transfer performance and refrigerant charge. A clean, correctly charged machine matches the manufacturer’s approach at design flow. A 5 K deviation is a stop signal.

Do I need a temporary chiller?

If the plant cannot tolerate a night without cooling, yes. A temporary machine or a remaining duty machine should carry the critical load. Do not plan a changeover with no backup.

What if full load is not available at night?

Use a temporary load bank or the process load. Do not open a bypass to fake load. A machine that has not run at 100% has not been proven.

What records should be handed over?

The switchover schedule, flush log, four-stage table, 24-hour trend and alarm list. These become the baseline for the next service.

What must be pre-tested?

Piping pressure test, pump rotation, valve stroke, sensor calibration and the control sequence. Pre-test before the shutdown window. A failed pre-test needs a second night.

How do I prove the changeover?

Run four load stages, record approach and power, and trend for 24 hours. A verbal handover is not proof. Compare with the design and the old plant.

Further technical reading

For the commissioning sequence, see Water Chiller Commissioning: Sequence, Measurements and Acceptance. For hold points, see Chiller Installation: 90 Days, Four Hold Points. For staging, see Chiller Part-Load Staging. For alarm response, see Chiller Alarm: The First 30 Minutes.