Temporary Hot Water for Construction Sites

A construction site is a moving load. The workforce may be 100 during foundations, 400 during structure and 200 during fit-out. Showers cluster into three hours after the evening shift. The mechanical room is often a site cabin with an unstable supply, no permanent foundation and a winter freeze risk.

A design copied from a permanent dormitory usually fails in two places: it sizes the heat pump on daily average and loses temperature at the evening peak, or it assumes a fixed mechanical room and cannot move the equipment when the site moves. The method below treats headcount as a schedule, capacity as a peak duty and the purchase decision as a duration question.

Size on the peak, not the daily average

Showering is concentrated between 18:00 and 21:00. If the daily heat is divided by 24 hours, the unit cannot keep up; tank temperature falls from 55 °C to below 40 °C and complaints begin. The correct sequence is: calculate the heat required during the three-hour peak, subtract what a storage tank can deliver, and let the heat pump recharge during the day and the low-tariff window.

For 300 people at 40 L/day, daily water is 12 m³. From 10 °C to 55 °C, the daily heat is 12,000 × 4.187 × 45 ÷ 3,600 = 628 kWh. If the unit had to deliver this in three hours, it would need 209 kW and the equipment cost would triple. The practical configuration is a 12 m³ tank and a unit running 10 hours, which needs 63 kW. With a winter ambient correction of 0.72, the nameplate becomes 87 kW, so select 2 × 45 kW.

The logic is “tank stores heat, unit replaces heat”. During the three-hour peak the unit keeps running while the tank discharges; tank temperature falls from 55 °C to about 45 °C and is restored the next day. The tank is not a luxury; it is the component that converts a 3-hour load into a 10-hour unit duty.

Peak headcount Daily water Daily heat Unit configuration Storage tank
100 4 m³ 209 kWh 1 × 30 kW 4 m³
300 12 m³ 628 kWh 2 × 45 kW 12 m³
500 20 m³ 1,047 kWh 2 × 75 kW 20 m³
800 32 m³ 1,675 kWh 4 × 65 kW 30 m³

Where the site provides laundry or canteen hot water, add 10–15 L per person. In southern summer, water use may rise by 20%, but the warmer makeup water reduces the heat demand.

Configure by phase, operate by actual headcount

Capacity follows the peak phase, operation follows the people on site. A foundation crew of 80–120 is stable and muddy, with longer showers; one unit at 50 °C is sufficient. Structural work at 200–400 is the design case, with both units running and low-tariff recharge. Fit-out at 150–250 fluctuates by gang rotation; run one unit and start the second on demand. Handover at 50–80 is intermittent.

Do not install the full peak configuration on day one if the first six months are a 100-person site. A modular package lets the second unit and tank section arrive with the structural phase. The electrical room and pipe headers should be sized for the final stage, however; retrofitting power capacity mid-project is more expensive than spare containment.

Equipment that can be moved

Portability is the first criterion on site, efficiency second. Choose split or modular units under 300 kg per section so two people and a small crane can load them. A monobloc is easier to transport but must go back to the factory for major repair, which a site cannot tolerate. Treat the casing for dust, and blow down the coils monthly.

Use bolted stainless panels for the tank. It can be dismantled into panels for transport and reassembled on the next site. Tank volume should be 80–100% of daily demand, higher than a permanent dormitory, because the peak is sharper and make-up capacity is weaker. Set the tank on a steel frame or concrete strip footing, never on backfill; settlement pulls the joints apart.

Use galvanized steel or PPR with flanged or clamp connections for easy modification. Bury insulated sections with waterproofing, support overhead pipe every 1.5 m, and protect against frost by insulation plus trace heating, nightly draining, or antifreeze in a separate circuit.

The site transformer is shared with welders and hoists. Select soft-start or inverter units and keep starting current below 1.5 times rated. Run the heat pump on a dedicated cable, not the welding circuit, and stagger start-up with the tower crane. A voltage drop below 10% causes repeated compressor protection and shortens life; a stabilizer is cheaper than a compressor.

Rent or buy

Projects run from six months to two years. The break-even depends on duration and residual value. For the 300-person package (2 × 45 kW and a 12 m³ bolted tank), purchase is about CNY 120,000 and rental about CNY 9,000 per month including installation and maintenance.

Option Outlay Suitable duration Note
Purchase CNY 120,000 Over 18 months Can move to the next site; residual about 50%
Rental CNY 9,000/month Under 12 months Includes installation and service; removal at end
Rent-to-buy First 6 months’ rent credited at 30% 6–18 months Must be written into the contract

Over 12 months, rental costs CNY 108,000. Purchase with 50% residual has a net cost of about CNY 60,000, so purchase wins. Over six months, rental is CNY 54,000 and purchase net is CNY 60,000, so rental is slightly ahead. The break-even is roughly 8–10 months, depending on whether the residual value can actually be realized.

Operating cost matters more than the rental decision. For the same 628 kWh/day of heat, a heat pump at COP 2.6 uses 242 kWh, about CNY 157/day or CNY 47,000 over 300 days at CNY 0.65/kWh. An electric heater at COP 1.0 uses 628 kWh, about CNY 408/day or CNY 122,000 a year. A diesel boiler at 85% efficiency uses about 74 L/day; at CNY 7.5/L that is CNY 555/day or CNY 167,000 a year. The heat pump saves about CNY 75,000 a year against electric heating and CNY 120,000 against diesel, which is why it can pay back even on a one-year project — provided the power is charged at construction tariff, not retail.

Four site problems

Frozen pipes: after a night shutdown, residual water freezes. Use insulation plus trace heating, keep a night circulation at no less than 5 °C, or drain the lines at the end of the shift. Most sites combine trace heating with draining because temporary insulation is rarely installed well.

Turbid water: the temporary supply carries sand and rust. Fit a Y-strainer at the inlet and a finer filter before the unit, and clean weekly. Very poor water needs a small softener, or the heat exchanger will block.

Low voltage: below 10% of rated voltage, the compressor will not start reliably. A dedicated cable and a stabilizer solve most cases. Do not enlarge the breaker to mask repeated protection.

Tank settlement: a tank on backfill tilts and leaks at the joints. Use a steel frame or concrete strip footing, and check level after the first fill.

Boundaries

The figures assume 40 L per person per day, a single three-hour evening peak and a 10 °C make-up in winter. A site with a night shift has two peaks and needs either a larger tank or a second heating window. A site above 1,500 m needs altitude derating, typically 8–12% at 2,000 m depending on the unit. A site with a generator instead of a grid supply needs a soft-start unit and a generator sized for starting current, not running current.

Common questions

What size heat pump for 300 workers?

At 40 L per person, daily water is 12 m³ and daily heat is 628 kWh. Running 10 hours needs 63 kW; with a 0.72 winter correction, select 2 × 45 kW and a 12 m³ tank. Add 10–15 L per person if laundry or canteen hot water is included.

Why is the tank larger than a permanent dormitory tank?

Because the peak is sharper and make-up is weaker. A site often has one inlet and unstable daytime pressure. Storage at 80–100% of daily demand shifts the peak into the low-tariff window and keeps temperature stable.

What if the pipes freeze overnight?

Use insulation plus trace heating, keep a small night circulation above 5 °C, or drain the lines after the shift. Temporary insulation is often poor, so trace heating plus draining is the common site combination.

Rent or buy for a 12-month project?

Rental is about CNY 108,000 for 12 months; purchase with 50% residual is about CNY 60,000 net. Purchase is usually better beyond 8–10 months, provided the unit can be moved to a next site and the residual value is real.

Why does the unit trip when the welders start?

They are likely sharing a circuit and the voltage dip is triggering compressor protection. Give the heat pump a dedicated cable, keep starting current below 1.5 times rated, and stagger start-up with welding and hoisting.

What happens to the equipment at project end?

Purchased units can move to the next site and the bolted tank can be dismantled; replace the gaskets. Rental units are removed by the supplier. Write the removal date and site reinstatement duty into the contract.

How do I size the peak?

Use the three-hour peak and the shift pattern, not the total headcount. Add 80–100% storage for showers. A camp that starts at 6 a.m. needs the tank ready before then.

Rent or buy?

Compare the rental period with an 8–10 month break-even. A short project rents; a long one buys. Include transport, installation and removal.