Sludge Dryer FAT: Eight Numbers, One Sludge Sample

A sludge dryer is a non-standard package. Two machines with the same “50 t/d” label can have different belt areas, different coil surfaces and different evaporation rates. The label is not a specification. The only reliable evidence is a loaded test on your sludge.

This article describes a factory acceptance test for a sludge dryer: the sample, the duration, the eight measurements and the contract terms that make the test enforceable. It is a witness protocol, not a factory audit.

Why the catalog number is not comparable

Fifty metric tons per day at 80% feed to 30% product evaporates 7.14 t/d. Fifty metric tons per day at 80% to 60% evaporates only 2.5 t/d. The same machine cannot do both in the same time. A supplier that quotes a feed rate without the moisture pair is quoting a label, not a performance.

The dryer’s real capacity is the evaporation rate, in kg water per hour, at a defined inlet moisture, outlet moisture and ambient condition. Ask for that number, and ask for the test that produced it.

The sample

Take 200–500 kg of the actual sludge from the project. Do not accept a substitute “similar” sludge; the polymer, fiber, sand and salt content change the belt behavior and the evaporation. Ship it in sealed drums, cool if the sludge is biological, and record the moisture on arrival. A sample that has dried in transit is not the feed.

If the project is small (below 10 t/d), the transport cost of a sample may be too high. In that case, use a site pilot or a reference site with the same sludge type, and state the substitution in the contract.

The test

Run the dryer for 4–8 hours at the design feed rate, with the design air temperature and the design belt speed. Start recording after the machine is stable, not from the first bucket. A stable run means the chamber temperature, the return-air humidity and the product moisture have stopped drifting.

No. Measurement Acceptance
1 Feed moisture Within 2 points of the project sample
2 Product moisture Contract value, fluctuation ≤3 points
3 Evaporation ≥95% of design
4 Specific energy Within 10% of the quoted kWh/t water
5 Product appearance Granular or loose, not sticky or caked
6 Condensate COD and ammonia near the design
7 Exhaust temperature and RH Matches the heat balance
8 Noise ≤85 dB(A) at 1 m

The two numbers that matter most are evaporation and specific energy. A supplier can define “capacity” as feed throughput and deliver only 60% of the evaporation. A supplier can define “energy” as the compressor only and omit the fan, pump and conveyor, which can add 30%.

Who records the data

The buyer’s technician should record the data, not only the seller’s commissioning engineer. Use calibrated scales for the feed and product, a calibrated power meter for the system, and a moisture oven or a calibrated analyzer. Take samples at the feed and discharge every 30 minutes, and keep them sealed.

Photograph the nameplate, the belt, the product and the power meter. A report without raw data is a brochure. A report with raw data can be audited.

Contract terms

Clause Write this If missing
Capacity and moisture Feed moisture range, product moisture, evaporation at the design point “50 t/d” is undefined
Energy kWh/t water, system boundary, test condition Compressor-only number hides the auxiliaries
Materials Grade and thickness of the wetted parts 201 stainless substituted for 304
Acceptance Run duration, sampling frequency, laboratory Each party samples differently
Spares and service Wearing parts list, response time, downtime remedy A broken flight stops the plant for weeks

Bind the three numbers: at 78–82% feed, the product is 30% or less, and the evaporation is at least 1,200 kg/h. A contract with only a product moisture limit is not enforceable, because the seller can choose a drier feed.

What a witness should watch

Watch the feed conveyor, not the control screen. A belt that is overloaded or a screw that is surging shows in the motor current and the product, not in the HMI. Watch the condensate drain: a trap that is pulling air will show bubbles or a hiss. Watch the product at the discharge: a sticky sheet that tears is a sign of under-drying or a polymer problem.

Ask for the alarm log. A test that is interrupted by a high-temperature or low-pressure alarm is not a pass. A test that runs with the safety interlock bypassed is not a test.

The test report should include the raw feed and product masses, the moisture method, the power meter reading, the ambient temperature and the alarm log. A one-page summary with a single efficiency number is not enough to prove a guarantee. Keep the raw sheets with the contract, because they are the evidence if the site performance later falls short.

Boundary

A factory test on 200–500 kg does not prove a full-scale continuous run. It proves the machine can evaporate at the design point on your sludge. The site loaded run still has to be done. For a very small project, a site pilot may replace the factory test; for a hazardous sludge, the factory test may need a licensed laboratory.

Common questions

Why is a catalog capacity not enough?

Because it does not state the feed and product moisture. 50 t/d at 80% to 30% evaporates 7.14 t/d; at 80% to 60%, only 2.5 t/d. The evaporation rate is the real capacity.

How much sludge should I send for a test?

200–500 kg of the actual sludge, in sealed drums. For a small project, a site pilot or a reference site may be cheaper, but the substitution must be stated in the contract.

How long should the test run?

4–8 hours after stable operation. A short spot test can pass and a longer run can expose a blocked belt or a drifting moisture. Record from stability, not from the first bucket.

What are the two key acceptance numbers?

Evaporation at least 95% of design and specific energy within 10% of the quoted kWh/t water. Both must state the system boundary, including fans, pumps and conveyors.

Who should record the data?

The buyer’s technician, with calibrated scales and a power meter. Photograph the nameplate and the raw data. A seller’s report without raw data is not auditable.

Can a factory test replace the site run?

No. It proves the machine on your sludge at the design point. The site loaded run still proves the feed system, the odor path and the continuous operation.

What should be in the FAT report?

Feed and product mass, moisture before and after, evaporation rate, power, inlet and outlet temperatures, ambient, and product appearance. Add the sludge source and the test duration. A report without these cannot be compared.

How many samples should I send?

At least 200–500 kg of representative sludge, in sealed containers, plus a small sample for analysis. Send it fresh or chilled. A grab sample from one point may not represent the feed.

Further technical reading

For the factory audit, see Sludge Dryer Manufacturer Audit. For commissioning, see Sludge Dryer Commissioning: Test Sequence and Acceptance Criteria. For specific energy, see Sludge Dryer Specific Energy. For fault codes, see Sludge Dryer Fault Codes and Troubleshooting.