The capacity limit of a combined cooling and heating unit is not the cooling capacity on the nameplate. It is the physical relationship between cooling and heat rejection: condenser heat equals cooling capacity plus input power, or about 1.25–1.3 times the cooling capacity. That number decides how much hot water can be produced as a by-product, and whether one machine can serve two processes at once.
The decision to use a combined unit depends on one question: do the cooling and heating loads overlap in time and are they close in magnitude? If they overlap and match, the recovered heat has somewhere to go. If they are offset or far apart, the condenser heat is either rejected or insufficient, and the unit degenerates into an ordinary chiller plus an ordinary boiler.
Four processes that genuinely need both
Injection molding. Mold cooling needs 15–20 °C chilled water, while hopper drying and mold preheating need 80–120 °C air or hot water. Both loads appear at start-up and remain stable while the presses run. This is the classic combined-unit application.
Food processing. Sterilization, cleaning and CIP need 60–85 °C hot water; cooling and pre-freezing need 2–7 °C chilled water. The hot-water demand is large but concentrated before and after the shift, so it partly offsets the cooling load and needs a storage tank to bridge.
Chemical reaction. A reactor needs cooling when it exudes heat, and heating for distillation, concentration or drying. Batch production alternates the two loads, so overlap is low; separate sources or a large heat store are usually more appropriate.
Hotels and hospitals. Air-conditioning chilled water is 7–12 °C and domestic hot water is 55–60 °C. In summer both run together and the condenser heat has a stable destination. In winter the cooling load falls and the heat pump is already in heating mode, so recovery adds little.
The common thread is a stable cooling load with a heat demand that overlaps it. Without that, the value of a combined unit is limited.
Heat balance you can recalculate
Example: an injection molding shop needs 100 kW of chilled water at 15 °C outlet. Select a combined unit with a cooling COP of 3.5.
Input power is 100 ÷ 3.5 = 28.6 kW. Condenser heat is 100 + 28.6 = 128.6 kW. That is the total heat available for recovery.
If the condenser heat raises 15 °C municipal water to 55 °C, the lift is 40 K. The available hot water is 128.6 ÷ (4.18 × 40) = 0.769 kg/s, or 2.77 m³/h.
Actual recovery is lower. Partial heat recovery takes only the desuperheating section and part of the condensing section, typically 15–25%. Full heat recovery uses a second condenser in series and recovers 60–80%. At 70% recovery, 90 kW is available, producing 1.94 m³/h at 55 °C; over 10 hours that is about 19 m³/day.
Compare with the avoided cost. Heating 1 t of water from 15 °C to 55 °C takes 46.5 kWh. A gas boiler at 90% efficiency and CNY 3.5/m³ gas costs about CNY 17–18 per metric ton. Avoiding 19 t/day saves about CNY 320/day. A full-recovery unit carries a 15–25% premium; on a 100 kW machine that is CNY 30,000–50,000, giving a payback of about 3–5 months at 10 hours/day.
The critical check is whether the shop can consume 19 m³/day. If it needs only 8 m³/day, the remaining condenser heat is still rejected, the effective recovery is lower, and the payback stretches beyond a year.
| Item | Value | Basis |
|---|---|---|
| Cooling capacity | 100 kW | Process load |
| Cooling COP | 3.5 | Selected unit |
| Input power | 28.6 kW | 100 ÷ 3.5 |
| Condenser heat | 128.6 kW | 100 + 28.6 |
| Hot water at 100% recovery | 2.77 m³/h | 128.6 ÷ (4.18 × 40) |
| Useful heat at 70% recovery | 90 kW | 128.6 × 0.7 |
| Hot water at 70% recovery | 1.94 m³/h | 90 ÷ (4.18 × 40) |
| Daily output over 10 h | 19 m³ | 1.94 × 10 |
Three recovery forms
No recovery is the right choice when there is no stable heat demand. The condenser heat goes to the atmosphere and the unit is a standard chiller.
Partial recovery adds a desuperheater on the compressor discharge line. It is simple, has little effect on the main cycle, and recovers 15–25% at 45–55 °C. It suits small or intermittent hot-water demand.
Full recovery uses two condensers in series: the hot-water side passes through the front condenser and the cooling side through the main condenser. Recovery is 60–80% at 50–60 °C, but control is more complex. If the hot-water temperature rises too high, the unit must switch to the main condenser or the high-pressure protection will trip.
| Form | Recovery | Hot water | Best for | Cost |
|---|---|---|---|---|
| None | 0 | — | No stable heat demand | Lowest |
| Partial | 15–25% | 45–55 °C | Small or intermittent demand | Low |
| Full | 60–80% | 50–60 °C | Large, continuous demand | 15–25% premium |
There is also a temperature ceiling. The condensing temperature sets the maximum hot-water outlet. An R410A unit producing above 60 °C needs a condensing temperature above 65 °C, which raises the pressure ratio and lowers COP. The economic outlet for full recovery is usually 50–55 °C; above that, add auxiliary heating rather than push the compressor.
Control logic and four cases to avoid
Control has three priorities. Cooling first: if the chilled-water temperature deviates, protect the cooling load and let heat recovery give way. Heat storage second: buffer hot water in a tank sized for 2–4 hours of demand. Heat backup third: if recovered heat is short, add auxiliary heat rather than over-speed the compressor.
Case one: heat demand far exceeds condenser heat. For example, 80 °C or higher hot water, or a demand three times the recoverable volume. A combined unit can cover only part, and the rest needs a boiler or high-temperature heat pump. The system becomes complex and separate sources are simpler.
Case two: cooling and heating are badly offset. If cooling runs by day and hot water is needed at night, there is no condenser heat at night and the recovery equipment is idle. The unit operates as a heat pump and the investment does not pay back.
Case three: small cooling load, large heat load. Condenser heat is tied to cooling capacity. A 20 kW chiller can provide at most about 25 kW of heat, which cannot serve a 100 kW demand.
Case four: very low chilled-water temperature. Processes needing below −10 °C have a high pressure ratio and high condensing temperature; heat recovery pushes discharge temperature further and destabilizes the unit. Use a separate low-temperature chiller and heat source.
| Check | Value | Meaning |
|---|---|---|
| Condenser heat | Cooling × (1 + 1/COP) | Upper limit of recoverable heat |
| Full recovery | Condenser heat × 0.6–0.8 | Usable heat |
| Hot water output | Recovered heat ÷ (4.18 × lift) | Compare with demand |
| Buffer tank | 2–4 hours of demand | Bridges offset |
| Hot water outlet | 50–55 °C | Above 60 °C COP falls sharply |
| Overlap | Hours per day | Below 4 h, re-evaluate |
| Heat coverage | Recovered ÷ demand | Below 30%, not economic |
Boundaries
The coefficients are typical for standard machines; the manufacturer’s recovery performance table governs. The gas price, electricity price and equipment premium should be replaced with project values. A combined unit is not a substitute for a boiler when the heat demand is high-temperature or highly seasonal. It is a heat-recovery device first and a heat source second.
Common questions
Can a combined unit produce chilled and hot water at the same time?
Yes, but hot-water volume is limited by condenser heat. Condenser heat is about 1.25–1.3 times cooling capacity, and full recovery takes 60–80% of it. A 100 kW chiller yields about 1.9 m³/h of 55 °C water; beyond that, add auxiliary heat.
Does heat recovery reduce cooling performance?
It can, depending on control. If hot-water temperature rises too high, condensing temperature and pressure ratio rise, and cooling capacity and COP fall. Set a hot-water upper limit, usually 55 °C, and switch to the main condenser with cooling priority.
Partial or full recovery?
Partial for small or intermittent demand, where low cost and simple retrofit matter. Full for large demand that overlaps cooling. The test is whether heat coverage can exceed 50%.
Is recovery useful in winter?
Usually not. Winter cooling load is small and the unit is already heating; recovery adds little. Do not count winter recovery in the energy saving.
Is a buffer tank necessary?
Recommended. Cooling and heating rarely match minute by minute. A 2–4 hour tank separates heat production from use and prevents condenser pressure from swinging with every draw.
Is a combined unit economic for injection molding?
Usually yes. Mold cooling and hopper drying run together, and both loads are stable. The recovered heat from 100 kW cooling covers a small hopper dryer, with payback often under a year.
When is heat recovery not worth it?
When cooling and heating loads rarely overlap, when the condenser heat is too low-grade, or when the distance to the heat user is long. Recover only the simultaneous load; storage can extend it but adds cost and losses.
How do I control simultaneous loads?
Use a heat-recovery chiller with a priority sequence: cooling first, then useful heat, then reject. Add a buffer tank and a backup heat source. Log the recovered energy so the saving can be verified.
Related reading
- Injection Molding Chiller Systems
- Chiller Cooling Load Calculation
- Chiller Selection Margins
- Food Processing Chiller Systems
Related reading
Heat pump vs gas boiler · Chiller plant group control · Air-cooled vs water-cooled