Why do cooling-load estimates differ so much?

Area index, diversity and fresh-air load are the usual causes. Corridors and mechanical rooms alone can change the total by 15%. Use an hourly calculation by orientation and floor.

Read the full technical article →
How many chillers should a plant have?

Two is the common start, so one can hold 60–70% of the load. Hospitals and data centers need N+1. Three or more suit a wide load swing.

Read the full technical article →
Is a magnetic-bearing chiller worth the premium?

Only where annual hours are long and the load swings widely. It can improve part-load IPLV by 20–30%, but costs over 50% more; short-hour projects rarely recover it.

Read the full technical article →
Air-cooled or water-cooled?

Above 3,000 hours with a tower and water, water-cooled usually wins on life-cycle cost. Below 1,500 hours, air-cooled avoids the tower and water treatment. Between, calculate 20 years.

Read the full technical article →
Why does a chiller trip the upstream breaker at start?

Two checks explain most start-up trips: the breaker instantaneous setting may sit below the inrush, or the supply transformer may be too small, so the bus voltage sags. Check the setting first, then the supply capacity.

Read the full technical article →
What maintenance is essential?

Log the operating data weekly, clean filters monthly, clean the condenser by differential, test the water quarterly and check insulation annually. These five catch most faults early.

Read the full technical article →
How do I test uptime?

Run the plant through the design day and a failure scenario. Verify the standby starts and the alarm reaches the operator. Uptime is a test, not a promise.

Read the full technical article →
What does surge sound like?

A low, muffled boom repeating every 1–3 seconds, often with pipe vibration. A continuous rumble or a bearing squeal is a different problem.

Read the full technical article →

Water chillers are specified on cooling load, part-load profile, condenser conditions and redundancy. This index groups the English guides by decision: working principle, selection and cost, alarms and water quality, then installation and retrofit.

Each link opens a full article with assumptions, formulas and site checks. For a project-specific answer, send the duty conditions through the contact page.